Jun 28, 2022
Construction Update - 6/24/2022
This past week's (6/20/22 to 6/25/22) scheduled work activities: G2 Going 100% clean booties required in this area. Final Paint Site...
emoryhsrb2
Jun 28, 2022
Construction Update - 6/17/2022
This past week's (6/13/22 to 6/18/22) scheduled work activities: G2 Office Furniture Installation. Cyclotron Lead & door operator ...
emoryhsrb2
Jun 28, 2022
Construction Update - 6/10/2022
This past week's (6/06/22 to 6/11/22) scheduled work activities: G2 Radiation Testing- Hot Cell/Cyclotron Systems. Stonehard Floor...
emoryhsrb2
Jun 28, 2022
Construction Update - 5/27/2022
This past week's (5/23/22 to 5/28/22) scheduled work activities: G2 Installation of toilet partitions. Installation of Cyclotron...
emoryhsrb2
Jun 27, 2022
Construction Update - 5/20/2022
This past week's (5/16/22 to 5/21/22) scheduled work activities: G2 Installation of lab casework benches Installation of Cyclotron...
emoryhsrb2
May 13, 2022
Construction Update - 5/13/22
This past week's (5/09/22 to /14/22) scheduled work activities: G2 Installation of lab casework benches Installation of Cyclotron...
emoryhsrb2
May 13, 2022
Construction Update - 5/06/2022
This past week's (5/02/22 to /07/22) scheduled work activities: G2 Installation of lab casework benches G1 Installation of ceiling grid...
emoryhsrb2
May 13, 2022
Construction Update - 4/29/2022
This past week's (4/25/22 to 4/30/22) scheduled work activities: G2 Installation of ceiling tiles. G1 Installation of ceiling grid in...
emoryhsrb2
Apr 18, 2022
Construction Update - 4/15/22
The traffic flow restrictions and lane reductions along Haygood Drive between Clifton and Ridgewood Drive that began on Tuesday 3/2/22...
emoryhsrb2
Apr 8, 2022
Construction Update - 4/09/2022
The traffic flow restrictions and lane reductions along Haygood Drive between Clifton and Ridgewood Drive that began on Tuesday 3/2/22...
emoryhsrb2
Apr 7, 2022
Construction Update - 4/01/2022
The traffic flow restrictions and lane reductions along Haygood Drive between Clifton and Ridgewood Drive that began on Tuesday 3/2/22...
emoryhsrb2
Apr 7, 2022
Construction Update - 3/25/2022
The traffic flow restrictions and lane reductions along Haygood Drive between Clifton and Ridgewood Drive that began on Tuesday 3/2/22...
emoryhsrb2
Apr 7, 2022
Construction Update - 3/18/2022
The traffic flow restrictions and lane reductions along Haygood Drive between Clifton and Ridgewood Drive that began on Tuesday 3/2/22...
emoryhsrb2
Apr 7, 2022
Construction Update - 3/11/2022
The traffic flow restrictions and lane reductions along Haygood Drive between Clifton and Ridgewood Drive that began on Tuesday 3/2/22...
emoryhsrb2
Apr 7, 2022
Construction Update - 3/04/2022
The traffic flow restrictions and lane reductions along Haygood Drive between Clifton and Ridgewood Drive that began on Tuesday 3/2/22...
emoryhsrb2
Apr 7, 2022
Construction Update - 2/25/2022
This past week's (2/21/22 to 2/26/22) scheduled work activities: G2 MEP connections to fume hoods underway. Installation of Biorepository...
emoryhsrb2
Feb 21, 2022
Construction Update - 2/18/2022
This past week's (2/14/22 to 2/19/22) scheduled work activities: G2 Installation of Bathroom Tile has been completed. Installation of...
emoryhsrb2
Feb 17, 2022
Construction Update - 2/11/2022
This past week's (2/07/22 to 2/12/22) scheduled work activities: G2 Fume Hood installation Installation of lighting in Hot cell area. G1...
emoryhsrb2
Feb 17, 2022
Construction Update - 2/4/2022
This past week's (1/31/22 to 2/05/22) scheduled work activities: G2 Biorepository Installation continues. Installation of lighting in Hot...
emoryhsrb2
Feb 17, 2022
Construction Update - 1/28/2022
This past week's (1/21/22 to 1/29/22) scheduled work activities: G2 Biorepository Installation continues. Installation of wall devices...