emoryhsrb2Oct 25, 2019Construction Update - 10/25/2019This past week’s (10/21 – 10/26) scheduled construction activities will include: Completed control pond and swale Completed mobilization...
emoryhsrb2Oct 18, 2019Construction Update - 10/18/19This week’s (10/14 – 10/18) scheduled construction activities included: Completed removal of abandoned cooling tower pipe. Completed...
emoryhsrb2Oct 18, 2019Construction Update - 10/11/19This week’s (10/7 – 10/11) scheduled construction activities included:: Tree removal on site continues. Small tree/shrub relocation...
emoryhsrb2Oct 18, 2019Construction Update - 10/4/19This week’s (9/30 – 10/4) construction activities: Grading Contractor (Dennis Taylor) will begin leveling of the site. Uncovering of...