emoryhsrb2Nov 5, 2020Construction Update - 9/25/2020The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...
emoryhsrb2Apr 24, 2020Construction Update - 4/18/2020The HSRB–II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...
emoryhsrb2Jan 31, 2020Construction Update - 1/31/2020This past week's (1/27/20 to 2/1/20) scheduled work activities: Deep excavation continues at the G2 Level of building. Installation of...
emoryhsrb2Oct 18, 2019Construction Update - 10/18/19This week’s (10/14 – 10/18) scheduled construction activities included: Completed removal of abandoned cooling tower pipe. Completed...
emoryhsrb2Oct 18, 2019Construction Update - 10/11/19This week’s (10/7 – 10/11) scheduled construction activities included:: Tree removal on site continues. Small tree/shrub relocation...
emoryhsrb2Oct 18, 2019Construction Update - 9/27/19This week’s (9/23 – 9/27) construction activities: Erosion/Sedimentation control fencing and other sediment control measures completed,...
emoryhsrb2Oct 18, 2019Construction Update - 9/20/19This week’s (9/16 – 9/20) construction activities: Site fence installation completed and installation of safety signage on exterior of...
emoryhsrb2Oct 18, 2019Construction Update - 9/6/19This week’s construction activities: Site fence installation began on 9/3/19. Delivery of JE Dunn office trailers began on 9/4/19. JE...