Construction Update - 9/6/19

This week’s construction activities:


  • Site fence installation began on 9/3/19.

  • Delivery of JE Dunn office trailers began on 9/4/19.

  • JE Dunn met with Emory PD to discuss safety concerns and site specific safety issues/policies.

  • Construction of the framing for installation of initial stone mockup began in front of HSRB-I

  • Erosion/Sedimentation control fencing and other sediment control measures began installation.

Next weeks scheduled construction activities will include:


  • Grading Contractor will begin leveling of the site.

  • Installation of site fencing will continue with fabric being hung on chain link fence.

  • JE Dunn Office Trailer installation will continue.

  • Tree removal begins.

  • Uncovering of abandoned chilled water pipes  (from Turman West) along Andrews Cir.

  • Begin early stages of work utility relocation near loading dock.

  • Removal of Patio furniture from outside of HSRB – I Café.

  • Preparation for removal of light poles on construction site will begin.