This week’s construction activities:
Site fence installation began on 9/3/19.
Delivery of JE Dunn office trailers began on 9/4/19.
JE Dunn met with Emory PD to discuss safety concerns and site specific safety issues/policies.
Construction of the framing for installation of initial stone mockup began in front of HSRB-I
Erosion/Sedimentation control fencing and other sediment control measures began installation.
Next weeks scheduled construction activities will include:
Grading Contractor will begin leveling of the site.
Installation of site fencing will continue with fabric being hung on chain link fence.
JE Dunn Office Trailer installation will continue.
Tree removal begins.
Uncovering of abandoned chilled water pipes (from Turman West) along Andrews Cir.
Begin early stages of work utility relocation near loading dock.
Removal of Patio furniture from outside of HSRB – I Café.
Preparation for removal of light poles on construction site will begin.