Construction Update - 3/5/2021



The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as we feel that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site will continue until further notice.


This past week's (3/1/21 to 3/06/21) scheduled work activities:

G2

  • Pouring Housekeeping pads for Air-Handling Units.

  • Overhead MEP work continues.

  • Layout of walls continues with installation of top tracks.

G1

  • Overhead MEP Rough-In Continues.

  • Layout of walls continues with installation of top tracks.

Level 1

  • Wall Layout and installation of top tracks began.

  • Removal of reshoring timbers was completed.

Level 2

  • Readying area for removal of shoring timbers supporting level 3 slab.

Level 3

  • Shoring timbers remain in place.

Level 4

  • Shoring timbers remain in place.

Level 5

  • Concrete pour Level 5 area 1 was completed.

  • Concrete pour in area 5-2 scheduled for Saturday 3/5/21.

  • Form work and rebar installation underway on level 5 areas 3, & 4.

  • Installing sleeves and insects in areas 5-3 & 5-4.

Site

  • Start of Andrews Circle grading work/road prep is underway.

  • Delivery on two APS’s for Micro-grid in generator yard on Friday 3/5/21.

  • Work on exterior mock up continues .

  • Work on Plaza retaining wall for driveway down to HSRB I & II loading docks continues.

Next week's (3/8/21 to 3/13/21) scheduled work activities:

G2 & G1

  • Overhead MEP rough-in continues.

  • Layout of interior walls continues.

  • Begin installation of fire caulking at some locations.

  • Delivery of large ductwork continues.

Level 1

  • Overhead MEP rough-in continues.

  • Layout of interior walls continues.

  • Drywall exterior sheathing underway.

  • Start of priority wall rough in has begun.

Level 2

  • Begin removal of reshoring timbers on level 2

Level 3

  • Shoring timbers remains in place

Level 4

  • Shoring timbers in place

Level 5

  • Forming of columns to support Level 6 slab in area 5-1, 5-2

  • Pour concrete slab in area 5-3.

Level 6

  • Installation of form work for Level 6 concrete slab begins.

Site

  • Continue work on retaining wall #2

  • Continue grading work on begin Andrews Circle curb and gutter on North edge (near CSX tracks) and asphalt base installation towards beginning of week (weather permitting).