emoryhsrb2Dec 9, 2019Construction Update - 12/6/19This past week's work (11/23 – 12/6) scheduled activities: Continue installation of underground storm lines. Installation of storm...
emoryhsrb2Nov 22, 2019Construction Update - 11/22/2019This past week’s (11/18 – 11/22) scheduled construction activities: Installation of Storm A-line install continues. Storm Detention...
emoryhsrb2Oct 18, 2019Construction Update - 9/27/19This week’s (9/23 – 9/27) construction activities: Erosion/Sedimentation control fencing and other sediment control measures completed,...
emoryhsrb2Oct 18, 2019Construction Update - 9/20/19This week’s (9/16 – 9/20) construction activities: Site fence installation completed and installation of safety signage on exterior of...
emoryhsrb2Oct 18, 2019Construction Update - 9/6/19This week’s construction activities: Site fence installation began on 9/3/19. Delivery of JE Dunn office trailers began on 9/4/19. JE...