Construction Update - 9/20/19

This week’s (9/16 – 9/20) construction activities:

  • Site fence installation completed and installation of safety signage on exterior of fence progressing. -- Additional blue wind screens are being installed.

  • Delivery and installation of all 8 of JE Dunn office trailers completed. -- Plumbing installation completed, electrical and data installation underway.

  • Erosion/Sedimentation control fencing and other sediment control measures completed, and inspected by City of Atlanta.

  • Locations for web-cameras identified and approved by Emory & CHOA.

  • Furniture on Patio outside of HSRB – I has been relocated.

Next week’s (9/23 - 9/27) scheduled construction activities will include:


  • Grading Contractor will begin leveling of the site, assuming City of Atlanta issues LDP permit as expected..

  • Tree removal will begin.

  • JE Dunn Office Trailer installation will continue with installation of electrical, phone, and data hook ups. -- Office furniture and set up of work stations and conference rooms will begin.

  • Uncovering of abandoned chilled water pipes  (from Turman West) along Andrews Cir. -- Abatement activities will begin 0n 10/1/19 once the pipes are carefully excavated.

  • Begin early stages of work for utility relocation near loading dock of HSRB - I