emoryhsrb2Jan 17, 2020Construction Update - 1/17/20.This past week's (1/13/20 to 1/17/20) scheduled work activities: Exploratory digging for the new loading dock entrance has begun....
emoryhsrb2Oct 18, 2019Construction Update - 10/18/19This week’s (10/14 – 10/18) scheduled construction activities included: Completed removal of abandoned cooling tower pipe. Completed...
emoryhsrb2Oct 18, 2019Construction Update - 10/11/19This week’s (10/7 – 10/11) scheduled construction activities included:: Tree removal on site continues. Small tree/shrub relocation...
emoryhsrb2Oct 18, 2019Construction Update - 9/27/19This week’s (9/23 – 9/27) construction activities: Erosion/Sedimentation control fencing and other sediment control measures completed,...
emoryhsrb2Oct 18, 2019Construction Update - 9/20/19This week’s (9/16 – 9/20) construction activities: Site fence installation completed and installation of safety signage on exterior of...