This past week's (1/13/20 to 1/17/20) scheduled work activities:
Exploratory digging for the new loading dock entrance has begun.
Installation of GAB and filter fabric over/around storm detention pipe at B line.
Maintenance of erosion control fencing and temporary detention pond.
Drilling (2 days) and blasting (1 day) during this past week.
Installation of access manholes for Storm detention at B – line.
Next week's (1/20/20 to 1/25/20) scheduled construction activities:
Deep excavation and haul off of material for G-2 level of building.
Continue backfill of storm detention B, assuming fill material dries out sufficiently.
Continue drilling and prepping for future blast on Tuesday & Thursday.
Installation of storm lines A-3 & A-4 continues.
Comments