Construction Update - 1/17/20.

This past week's (1/13/20 to 1/17/20) scheduled work activities:

  • Exploratory digging for the new loading dock entrance has begun.

  • Installation of GAB and filter fabric over/around storm detention pipe at B line.

  • Maintenance of erosion control fencing and temporary detention pond.

  • Drilling (2 days) and blasting (1 day) during this past week.

  • Installation of access manholes for Storm detention at B – line.

Next week's (1/20/20 to 1/25/20) scheduled construction activities:

  • Deep excavation and haul off of material for G-2 level of building.

  • Continue backfill of storm detention B, assuming fill material dries out sufficiently.

  • Continue drilling and prepping for future blast on Tuesday & Thursday.

  • Installation of storm lines A-3 & A-4 continues.