emoryhsrb2Oct 18, 2019Construction Update - 10/4/19This week’s (9/30 – 10/4) construction activities: Grading Contractor (Dennis Taylor) will begin leveling of the site. Uncovering of...
emoryhsrb2Oct 18, 2019Construction Update - 9/20/19This week’s (9/16 – 9/20) construction activities: Site fence installation completed and installation of safety signage on exterior of...
emoryhsrb2Oct 18, 2019Construction Update - 9/6/19This week’s construction activities: Site fence installation began on 9/3/19. Delivery of JE Dunn office trailers began on 9/4/19. JE...