emoryhsrb2Jan 17, 2020Construction Update - 1/17/20.This past week's (1/13/20 to 1/17/20) scheduled work activities: Exploratory digging for the new loading dock entrance has begun....
emoryhsrb2Jan 10, 2020Construction Update - 1/10/20This past week's (1/6/20 to 1/11/20) scheduled work activities: Continued installation of Storm detention system pipe on B – Line. Began...