This past week's (1/6/20 to 1/11/20) scheduled work activities:
Continued installation of Storm detention system pipe on B – Line.
Began covering and back filling completed sections of pipe.
Continued drilling of subsurface rock for next rounds of blasting.
Maintenance and reinforcing of site erosion fencing in anticipation of upcoming storms.
Next week's (1/13/20 to 1/20/20) scheduled construction activities:
Deep excavation and haul off of building pad site will begin.
Backfill (covering) of storm detention pipe along B line will continue.
Drilling of subsurface rock will continue.
Installation of storm water piping/structures for along D-1, A-3 and A-4 will continue.