top of page
  • Writer's pictureemoryhsrb2

Construction Update - 1/10/20

This past week's (1/6/20 to 1/11/20) scheduled work activities:

  • Continued installation of Storm detention system pipe on B – Line.

  • Began covering and back filling completed sections of pipe.

  • Continued drilling of subsurface rock for next rounds of blasting.

  • Maintenance and reinforcing of site erosion fencing in anticipation of upcoming storms.


Next week's (1/13/20 to 1/20/20) scheduled construction activities:

  • Deep excavation and haul off of building pad site will begin.

  • Backfill (covering) of storm detention pipe along B line will continue.

  • Drilling of subsurface rock will continue.

  • Installation of storm water piping/structures for along D-1, A-3 and A-4 will continue.

32 views0 comments

Recent Posts

See All

Commentaires


bottom of page