The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The team will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.
This past week's (9/21/20 to 9/26/20) scheduled work activities:
G2:
No new activities in this area this week.
G1:
Concrete Slab Pour 2 Stone Fill
Concrete Slab Pour 4 Electrical Rough In
Concrete Slab Pour 4 Reinforcing
Concrete Slab Pour 4 Plumbing
Concrete Slab Pour 4 Waterproofing
Concrete pour at section of North foundation wall
Level 1:
Reinforcing for Elevated Concrete Deck Pour 4
Next week's (9/28/20 to 10/03/20) scheduled work activities:
G2:
Backfilling of G2 Continuous Foundation Walls Continues
Finished Stripping Shoring
G1:
Installation of North Foundation Walls Continues
Pouring of Slab on Grade Pour 4 East
Backfill of G1 Slab on Grade Pour 4 West Starts
Slab on Grade Pour 2 Underground MEP Installation Continues
Level 1
Forming Level 1 Pour 4 Finishes
Reinforcing for Level 1 Pour 4 Starts
HSRB – I Vivarium Expansion:
Excavation of Spread Footings Begins
Forming of Spread Footings Begins