Construction Update - 9/25/2020


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The team will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.

This past week's (9/21/20 to 9/26/20) scheduled work activities:


G2:

  • No new activities in this area this week.

G1:

  • Concrete Slab Pour 2 Stone Fill

  • Concrete Slab Pour 4 Electrical Rough In

  • Concrete Slab Pour 4 Reinforcing

  • Concrete Slab Pour 4 Plumbing

  • Concrete Slab Pour 4 Waterproofing

  • Concrete pour at section of North foundation wall

Level 1:

  • Reinforcing for Elevated Concrete Deck Pour 4

Next week's (9/28/20 to 10/03/20) scheduled work activities:


G2:

  • Backfilling of G2 Continuous Foundation Walls Continues

  • Finished Stripping Shoring

G1:

  • Installation of North Foundation Walls Continues

  • Pouring of Slab on Grade Pour 4 East

  • Backfill of G1 Slab on Grade Pour 4 West Starts

  • Slab on Grade Pour 2 Underground MEP Installation Continues

Level 1

  • Forming Level 1 Pour 4 Finishes

  • Reinforcing for Level 1 Pour 4 Starts

HSRB – I Vivarium Expansion:

  • Excavation of Spread Footings Begins

  • Forming of Spread Footings Begins