top of page
  • Writer's pictureemoryhsrb2

Construction Update - 5/21/21


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as we feel that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site will continue until further notice.


This past week's (5/17/21 to 5/22/21) scheduled work activities:

G2/G1

  • Overhead MEP installation continues G-1 & G-2.

  • Plumbing in wall rough in G-1.

  • Started Catwalk sequence #3.

  • Electrical Room Build out G -1 & G-2.

  • Detailing Catwalk mezzanine G-1.

  • Framing Headers for Hot Cells G-1.

  • Framing Elevator shafts G-1.

  • Continue framing of walls in area 3 G-1.

Level 1

  • Level 1 South Non-priority wall framing.

  • Overhead MEP installation Continues.

  • In Wall MEP Installation continues.

Level 2

  • MEP installation & Sheet metal HVAC ductwork rough-in continues.

  • In wall MEP work continues.

  • Fire suppression work continues – Area C.

  • Level 2 non-priority wall walling underway.

Level 3

  • Overhead MEP Installation continues.

  • Stair installation underway – North Tower.

  • Installation of steel beams for East bridges continues

Level 4

  • Priority wall framing, North Tower Area D.

  • Overhead MEP installation – Areas C & D.

  • Removal of reshoring – South Tower.

Level 5

  • Removal of reshoring – South tower.

  • Overhead MEP Installation underway.

  • Installation of stairs on L5 continues.

Level 6

  • Removal or reshoring – South tower.

  • Concrete poured over metal decking on L-6 West Bridge.

Mechanical Penthouse

  • Parapet Concrete pour #4.

Site

  • HSRB – I & II driveway and loading dock concrete pour completed. Loading docks reopened on 5/17/21.

Skin:

  • Granite Installation has begun along Andrews Circle.

  • CNU installation continues on North exterior elevation.

Next week's (5/24/21 to 5/29/21) scheduled work activities:

G2 & G1

  • Granite installation will continue along Andrews Circle begins.

  • Overhead MEP installation continues G2 & G1.

  • Plumbing in wall rough in continues on G-1.

  • Finishing detailing entry to mechanical Mezzanine- G 1.

  • Start catwalk sequence #4.

Level 1

  • Overhead MEP installation continues.

  • In wall MEP installation continues.

  • Level 1 South non-priority wall framing continues.

Level 2

  • Overhead MEP Installation continues.

  • Installation of exterior CMU walls and grouting continues.

  • Exterior Framing West elevation.

Level 3

  • Installation of exterior CMU walls and grouting continues.

  • Overhead MEP work continues.

Level 4

  • Priority wall framing- Area C.

  • Installing NW duct shaft separator steel L4 to penthouse.

  • Set stairs N1 L3 to penthouse.

Level 5

  • Installation of Overhead MEP has begun.

Level 6

  • Exterior drywall framing – L6 North Tower.

  • Overhead Plumbing installation has begun.

Mechanical Penthouse

Site

  • Granite installation along Andrews Circle will continue.



43 views0 comments

Recent Posts

See All

Comments


bottom of page