Construction Update - 5/7/21


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as we feel that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site will continue until further notice.


This past week's (5/03/21 to 5/08/21) scheduled work activities:

G2/G1

  • Overhead MEP installation continues G-1 & G-2.

  • Framing of headers for glass opens on G-2.

  • Fire Suppression installation at loading dock G-2 level.

  • Electrical room build V157 out G-1.

  • Vivarium AHU (Air Handling Unit) build out G-1.

  • Installation of exterior framing in public lobby G-1.

  • Continued framing of walls in area 3 on G-1.

  • Starting installation of catwalk above BSL3 Labs.

Level 1

  • Installation of non-priority walls South Tower Area A.

  • Overhead MEP installation Continues.

  • In Wall MEP Installation continues.

  • Installation of fire suppression piping in area B.

  • Window installation continues.

Level 2

  • MEP installation & Sheet metal HVAC ductwork rough-in continues.

  • Framing of exterior windows – North Tower area C.

  • Installation of exterior CMU – North Tower area C.

Level 3

  • Overhead MEP Installation continues.

  • Top out priority walls South tower Area B.

  • Installation of overhead framing at Exterior walls.

  • Installing exterior CMU walls- North Tower – Area C.

Level 4

  • Frame and top out priority walls, North Tower Area D.

Level 5

  • Remove remaining wood shoring still in place at North Tower.

Level 6

  • Remove remaining wood shoring still in place at North Tower

Mechanical Penthouse

  • Pouring of concrete pads in North Tower.

  • Rebar installation in pour #3 & #4 area.

Site

  • Installation of new concrete drive and pads at loading docks for HSRB – I & HSRB – II began.

Next week's (5/10/21 to 5/17/21) scheduled work activities:

G2 & G1

  • Granite installation along Andrews Circle begins.

  • Starting catwalk installation in area #2 G-1.

  • Complete installation of catwalk in area #1 G-1.

  • Overhead MEP installation continues G2 & G1.

  • Installation of fire suppression piping G-1.

Level 1

  • Non-priority wall installation – South tower area B.

  • Overhead MEP installation continues.

  • In wall MEP installation continues.

  • Window installation continues.

  • Curtain wall installation begins on North Tower.

Level 2

  • Overhead MEP Installation continues.

  • Framing exterior windows - North tower area C.

  • Installing exterior CMU North tower Area C.

Level 3

  • Framing Exterior windows- North Tower area C.

  • Installation of Exterior CMU walls - North Tower area C.

  • Overhead MEP work continues.

Level 4

  • Frame and top out priority walls – North Tower.

  • Remove wood shoring area A

Level 5

  • Layout and install top track – North Tower.

  • Removal of wood shoring south tower area A.

Level 6

  • Layout top track – North Tower.

  • remove wood shoring – South Tower area A.

Mechanical Penthouse

  • Concrete pour area #3 and area 4.

  • Parapet concrete pour – North Tower.

  • Delivery and setting of office air handling units on penthouse level.

Site

  • Continue work on installation of new loading dock area concrete.





14 views0 comments