Construction Update - 5/14/21

Writer's picture: emoryhsrb2emoryhsrb2

The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as we feel that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site will continue until further notice.


This past week's (5/10/21 to 5/15/21) scheduled work activities:

G2/G1

  • Overhead MEP installation continues G-1 & G-2.

  • Fire Suppression installation at G-1 level.

  • Started Catwalk sequence #2.

  • Completed details on sequence #1 by catwalk elevator.

Level 1

  • Non-priority wall Installation South Tower Area B.

  • Overhead MEP installation Continues.

  • In Wall MEP Installation continues.

  • Window installation continues.

Level 2

  • MEP installation & Sheet metal HVAC ductwork rough-in continues.

  • Curtain wall installation Begins North Tower.

  • Installation of exterior CMU – North Tower area C.

Level 3

  • Overhead MEP Installation continues.

  • Framing exterior windows – North Tower Area C.

  • Installing exterior CMU walls- North Tower – Area C.

  • Work on installation of East bridges iron continues.

Level 4

  • Frame and top out priority walls, North Tower Area D.

  • Framing exterior windows – North Tower Area D

Level 5

  • Layout wall top track – North tower.

Level 6

  • Layout to track – North tower.

Mechanical Penthouse

  • Poured concrete pour #3, #4 scheduled for Tuesday AM.

  • Pour concrete parapet – North tower.

  • Installation of 3 North Tower Air Handler Units (AHU).

Site

  • 50% of new driveway and loading dock areas to HSRB – I & II were poured this past week.

  • View of West end of building from Andrews Circle

  • Skin: Granite Installation has begun along Andrews Circle.

Next week's (5/17/21 to 5/22/21) scheduled work activities:

G2 & G1

  • Granite installation will continue along Andrews Circle begins.

  • Starting catwalk sequence #3 G-1.

  • Electrical room build outs continue level G1 & 2.

  • Overhead MEP installation continues G2 & G1.

  • Plumbing in wall rough in continues on G-1.

  • Framing elevator shafts – G – 1.

  • Framing headers for Hot Cell installation.

  • Continue wall framing in area 3 G-1 level.

Level 1

  • Non-priority wall installation – South tower area continues.

  • Overhead MEP installation continues.

  • In wall MEP installation continues.

  • Window installation continues.

Level 2

  • Overhead MEP Installation continues.

  • Framing exterior windows - North tower area C.

  • Installing exterior CMU North tower Area C.

Level 3

  • Framing Exterior windows- North Tower.

  • Installation of Exterior CMU walls - North Tower area C.

  • Overhead MEP work continues.

  • Stair installation North Tower.

Level 4

  • Frame and top out priority walls – North Tower area D..

  • Overhead MEP installation areas C & D.

  • Removal of reshoring South tower.

Level 5

  • Installation of Overhead MEP Hangers Areas C & D.

  • Removal of wood shoring South Tower.

Level 6

  • Layout top track – North Tower.

  • Remove wood shoring – remainder of South Tower.

Mechanical Penthouse

  • Concrete pour area #4 Tuesday 5/18/21.

  • Parapet concrete pour – South Tower.

Site

  • Continue work on installation of new loading dock area concrete.

  • Granite installation along Andrews Circle will continue.