top of page
  • Writer's pictureemoryhsrb2

Construction Update - 5/06/2022



This past week's (5/02/22 to /07/22) scheduled work activities:

G2

  • Installation of lab casework benches

G1

  • Installation of ceiling grid in G – 1 Lobby.

  • Installation of ceiling tiles in BSL area.

  • 7 T Overhead MEP rough – in underway.

  • Techniplast delivery was made and installation begun.

  • Installation of case work continues.

Level 1

  • 9 wood ceiling installation continues.

  • Furniture installation has concluded.

  • Installation of lab casework continues.

  • Construction Clean of L1 Wet labs underway.

  • Drywall finishing at East Pedestrian bridge(s) Continues.

  • Removal of scaffolding in Atrium underway. View from L1 up to skylight.

Level 2

  • Plumbing fixture installation underway.

  • Application of final coat of paint underway.

  • Installation of 9 wood ceilings underway.

  • Installation of Carpet in L 2 offices and meeting rooms underway.

Level 3

  • Finishing Installation of Canopy Hooks.

  • Framing of monumental Stairs underway.

Level 4

  • Phoenix Valve Start up and framing underway.

  • Lab Casework install continues.

  • Dropping ceiling tiles North & South Wings.

Level 5

  • ACT installation in North Wing.

  • Atrium Soffit framing continues.

  • Installing of Lab casework underway.

Level 6

  • Installation of Balcony glass underway.

  • Lab Case work was delivered to site.

Mechanical Penthouse

  • Installation of Terracotta tiles on exterior of mechanical penthouses continues.

  • Installation of metal panels on the interior and exterior parapet walls continues.

  • TPO & mod- bit roof installation continues.

  • Installation of East Trellis continues

  • Installation of traffic coating on Penthouse floor has begun.

Skin:

  • Marble installation continues on South & SW Façade of South Tower @ MC #7, 8, 11 & #12.

  • Installation of granite continues on the North elevation of building.

  • Installation of Rosa Borba at SW Entry continues.

HSRB – I Vivarium Expansion:

  • Stonhard floor installation is underway.

  • Installation of utility connections to HSRB – I continue.

Site:

  • Installation of trees on plaza level continues.

  • Installation of new curbs along Andrews Circle has begun.

Next week's (5/02/22 to 5/07/22) scheduled work activities:

G2

  • Installation of Lab casework and benches continues.

G1

  • Plumbing Fixture installation continues.

  • 7-T MRI MEP overhead rough in continues.

  • Techniplast equipment install continues.

Level 1

  • 9 wood ceiling installation continues.

  • Lab Tables and bench installation to begin

Level 2

  • Plumbing fixture installation to continue

  • Installation of 9 wood ceilings to continue.

Level 3

  • Finish installation of Canopy hoods.

  • Framing of monumental stairs to continue.

  • Carpet installation in North Offices.

Level 4

  • Fume Hood tie ins.

  • Fire Alarm & Lighting control wiring.

Level 5

  • Installation of Interior atrium glass.

  • Lab case work installation continues.

  • Atrium soffit framing continues.

Level 6:.

  • Atrium Soffit Framing.

  • ACT Grid and Hard Ceiling Installation.

  • Lab Case work delivery & Install.

Mechanical Penthouse

  • Interior and exterior parapet metal panel installation continues.

  • Terra Cotta Installation on North & South Penthouse continues.

  • Mod – bit & TPO roof installation continues.

  • East Trellis installation begins.

  • Louver Installation to begin.

Skin

  • Marble installation continues on MC # 7, 8, 11, & 12 (master climber).

  • Granite installation at North elevation continues.

  • Installation of Rosa Borba to continue.

HSRB – I Vivarium Expansion:

  • Installation of Stonehard Epoxy flooring to conclude.

Site:

  • Andrew Circle South Curb installation to begin.



31 views0 comments

Recent Posts

See All
bottom of page