This past week's (5/02/22 to /07/22) scheduled work activities:
G2
Installation of lab casework benches
G1
Installation of ceiling grid in G – 1 Lobby.
Installation of ceiling tiles in BSL area.
7 T Overhead MEP rough – in underway.
Techniplast delivery was made and installation begun.
Installation of case work continues.
Level 1
9 wood ceiling installation continues.
Furniture installation has concluded.
Installation of lab casework continues.
Construction Clean of L1 Wet labs underway.
Drywall finishing at East Pedestrian bridge(s) Continues.
Removal of scaffolding in Atrium underway. View from L1 up to skylight.
Level 2
Plumbing fixture installation underway.
Application of final coat of paint underway.
Installation of 9 wood ceilings underway.
Installation of Carpet in L 2 offices and meeting rooms underway.
Level 3
Finishing Installation of Canopy Hooks.
Framing of monumental Stairs underway.
Level 4
Phoenix Valve Start up and framing underway.
Lab Casework install continues.
Dropping ceiling tiles North & South Wings.
Level 5
ACT installation in North Wing.
Atrium Soffit framing continues.
Installing of Lab casework underway.
Level 6
Installation of Balcony glass underway.
Lab Case work was delivered to site.
Mechanical Penthouse
Installation of Terracotta tiles on exterior of mechanical penthouses continues.
Installation of metal panels on the interior and exterior parapet walls continues.
TPO & mod- bit roof installation continues.
Installation of East Trellis continues
Installation of traffic coating on Penthouse floor has begun.
Skin:
HSRB – I Vivarium Expansion:
Stonhard floor installation is underway.
Installation of utility connections to HSRB – I continue.
Site:
Installation of trees on plaza level continues.
Installation of new curbs along Andrews Circle has begun.
Next week's (5/02/22 to 5/07/22) scheduled work activities:
G2
Installation of Lab casework and benches continues.
G1
Plumbing Fixture installation continues.
7-T MRI MEP overhead rough in continues.
Techniplast equipment install continues.
Level 1
9 wood ceiling installation continues.
Lab Tables and bench installation to begin
Level 2
Plumbing fixture installation to continue
Installation of 9 wood ceilings to continue.
Level 3
Finish installation of Canopy hoods.
Framing of monumental stairs to continue.
Carpet installation in North Offices.
Level 4
Fume Hood tie ins.
Fire Alarm & Lighting control wiring.
Level 5
Installation of Interior atrium glass.
Lab case work installation continues.
Atrium soffit framing continues.
Level 6:.
Atrium Soffit Framing.
ACT Grid and Hard Ceiling Installation.
Lab Case work delivery & Install.
Mechanical Penthouse
Interior and exterior parapet metal panel installation continues.
Terra Cotta Installation on North & South Penthouse continues.
Mod – bit & TPO roof installation continues.
East Trellis installation begins.
Louver Installation to begin.
Skin
Marble installation continues on MC # 7, 8, 11, & 12 (master climber).
Granite installation at North elevation continues.
Installation of Rosa Borba to continue.
HSRB – I Vivarium Expansion:
Installation of Stonehard Epoxy flooring to conclude.
Site:
Andrew Circle South Curb installation to begin.