Construction Update - 5/13/22


This past week's (5/09/22 to /14/22) scheduled work activities:

G2

  • Installation of lab casework benches

  • Installation of Cyclotron continues

G1

  • Installation of ceiling grid in G – 1 Lobby continues.

  • trim out continues in BSL 3 areas.

  • Work in 7 T suite continues in preparation of delivery on 5/14/22

  • Work in 3 T suite continues.

  • Techniplast installation in aquatics suite continues.

  • Installation of case work continues various locations.

Level 1

  • 9 wood ceiling installation continues.

  • Furniture installation has concluded part 1 of installation.

  • Installation of lab casework continues Lab table and benches.

  • Installation of 9 wood ceiling continues on L 1..

  • Drywall finishing at East Pedestrian bridge(s) Continues.

  • Removal of scaffolding in Atrium has finished.

Level 2

  • Plumbing fixture installation continues

  • Application of final coat of paint underway.

  • Installation of 9 wood ceilings continues.

  • Installation of furniture in write up areas and offices underway.

Level 3

  • Final coat of paint underway.

  • Monumental stair framing underway.

  • Carpet installation in North Offices has begun.

  • Installation of selected mill work has begun

Level 4

  • Fire alarm and lighting control wiring underway.

  • Fume hood tie ins continue.


Level 5

  • Atrium soffit Framing underway.

  • Interior atrium glass and handrailing continues.

  • Lab casework installation continues.

Level 6

  • Atrium Soffit framing continues.

  • Lab Case work was delivered, installation to begin.

  • ACT grid and hard ceiling installations underway.

Mechanical Penthouse

  • Installation of Terracotta tiles on exterior of mechanical penthouses continues.

  • Installation of metal panels on the interior and exterior parapet walls continues.

  • TPO & mod- bit roof installation continues.

  • Installation of East Trellis continues.

  • Delivery and installation of HVAC Louvers began on Thursday, 5/12/22.

Skin:

  • Marble installation continues on South & SW Façade of South Tower @ MC 11 & #12.

  • Installation of granite continues on the North elevation of building.

  • Installation of Rosa Borba at SW Entry continues.

  • Installation of glass on East Connector bridges continues.

HSRB – I Vivarium Expansion:

  • Stonhard floor installation is continues.

  • Installation of utility connections to HSRB – I continue.

Site:

  • Installation of trees on plaza level continues.

  • Installation of new curbs along Andrews Circle continues.

Next week's (5/16/22 to 5/21/22) scheduled work activities:

G2

  • Device trim out to continue.

G1

  • 7-T suite build out to continue.

  • 7-T MRI delivery and set up.

  • 3-T MRI MEP rough in to continue.

  • BSL trim out to continue.

Level 1

  • 9 wood ceiling installation continues.

  • Lab Tables and bench installation to continue.

Level 2

  • Atrium soffit Finishing.

  • Installation of 9 wood ceilings to continue.

  • Lab table installation.

  • Glass handrail installation to continue.

Level 3

  • Installation of Flooring in North Offices.

  • Final paint coat to be applied.

Level 4

  • Atrium soffit framing to continue.

  • Device trim out to continue.

Level 5

  • Sterilizer MEP connections underway.

  • Lab case work installation continues.

  • Ceiling tile installation.

Level 6:.

  • Prime paint South Labs.

  • Final Coat paint at doors and frames.

  • ACT device out continues.

Mechanical Penthouse

  • Interior and exterior parapet metal panel installation continues.

  • Terra Cotta Installation on North & South Penthouse continues.

  • Mod – bit & TPO roof installation continues.

  • East Trellis installation to continue.

  • Louver Installation to continue.

  • AHU damper installation to begin.

Skin

  • Marble installation continues on MC 11, & 12 (master climber).

  • Granite installation at North elevation continues.

  • Installation of Rosa Borba to continue.

HSRB – I Vivarium Expansion:

  • ACT ceiling grid installation to begin..

Site:

  • Cellular concrete installation at plaza level to begin.

  • Side walk layout install at East Plaza to begin.


100 views0 comments