Construction Update - 3/18/2022


The traffic flow restrictions and lane reductions along Haygood Drive between Clifton and Ridgewood Drive that began on Tuesday 3/2/22 are the results of a DeKalb County Water line installation project.


This work is being managed by DeKalb County and not Emory's Planning, Design, and Construction Department.


We are told that weather permitting the project will take between 6 – 8 weeks and will be completed prior to Emory's Graduation weekend activities.

This past week's (3/14/22 to 3/19/22) scheduled work activities:

G2

  • Fume Hood monitor & Sash Sensor Installation underway.

  • Specialty Gas Rough- In & Radio-pharmacy Casework Installation underway.

  • Installation of Biorepository continues.

  • Breakroom Millwork installation has begun.

G1

  • FRP door installation has begun.

  • Breakroom mill work installation has begun.

  • Installation of BSL sealants is underway.

  • Vivarium device trim out continues.

  • Installation of Techniplast aquatics equipment has begun.

  • 7T MRI Slab has been repoured.

  • Overhead door installation continues.

  • Framing of walls in CSI reception area continues on G1.

  • Installation of monumental stairs from G1 to L1 continues.

Level 1

  • Controlled Environmental Room Installation continues.

  • MEP connections to Sterilizers continues.

  • Fixture and device trim out continues.

  • Installation of Store front doors.

  • Installation of the Glazing at the East connector bridges continues.

  • Installation of East monumental stairs continues.

Level 2

  • Installation of Store front doors.

  • Installation of glass at atrium window walls for computational lab areas.

  • Installation of glass handrail has begun.

  • Installation of fixed casework in wet labs continues.

  • Controlled Environmental Room Installation continues

Level 3

  • Installation of Atrium interior store front glass continues.

  • Installation of store front doors.

  • Fume hood delivery

  • Fixed casework and epoxy top delivery.

Level 4

  • Prime & First coat of finish paint in North Tower areas.

  • Starting installation of ACT grids – North wing,

  • Installation of air distribution grilles continues.

Level 5

  • Prime Paint in South Wing .

  • Installation of fan coil units.

  • Installation of 5 building elevators continues.

  • Installation of ACT grids.

Level 6

  • Finishing the ceiling in the West atrium.

  • Started installation of drywall on one side of each framed wall ("one siding drywall") in South Wing.

  • Eyebrow and roof drain installation continues.

  • hanging drywall North.

  • Wall cover up inspection - South wing.

  • Work continues on the interior of the skylight

Mechanical Penthouse

  • Installation of Terracotta tiles on exterior of mechanical penthouses continues.

  • Installation of metal panels on the interior and exterior parapet walls continues.

  • Exterior Eyebrow metal panels is underway at MC 1 to 4.

  • Air Handling Units (AHU) device installation continues.

  • TPO roof installation continues on the South Penthouse roof.

  • Installation of Doghouses next to exterior of skylight continues

Skin:

  • Marble installation continues on South & SW Façade of South Tower @ MC #9, #10 & #11.

  • Installation of curtainwall glass at Pedestrian bridges continues.

  • Installation of glass at Structural curtain wall scheduled to be completed Saturday.

HSRB – I Vivarium Expansion:

  • Installation of overhead MEP pipes continues.

  • Framing of walls in interior of space continues.

  • HVAC ductwork pressure testing is underway.

  • In wall MEP rough in underway.

  • Installation of utility connections to HSRB – I are underway.

  • Installation of Drywall continues in select areas.

Site:

  • Installation of light weight soils for plaza areas continues.

Next week's (3/21/22 to 3/26/22) scheduled work activities:

G2

  • Installation of Biorepository to continues.

  • Wood Door installation begins.

  • GE remobilization to resume cyclotron installation.

G1

  • Wood door installation begins.

  • FRP door installation continues.

  • Vivarium device trim out continues

  • Monumental stair installation continues. G1 to L1

  • BSL Sealants continue.

Level 1

  • Fixture and Device trim out continues.

  • Level 1 North & South Wings ACT Tile installation.

Level 2

  • Plumbing fixture installation begins.

  • Atrium electrical rough in begins.

  • Installation of finishes for Wonder Wall.

  • Fixture & Device trim out continues.

  • Installation of CSP adaptors.

Level 3

  • Tie in Fume hoods.

  • Delivery of fixed casework and epoxy tops continues.

Level 4

  • Installation of glass handrails – center atrium.

  • Installation of air distribution grills continues.

  • ACT Rough in and trim out.

Level 5

  • Installation of Fan Coil Units.

  • Prime & Paint continues South Wing.

  • Installation of ACT Grids – South Wing.

Level 6:.

  • Eyebrow and roof drain installation

  • Hanging dry wall – South Wing.

  • ACM Installation at Eyebrow.

Mechanical Penthouse

  • Interior and exterior parapet metal panel installation continues.

  • Terra Cotta Installation on North Penthouse continues.

  • Mechanical tie ins to exhaust air units. AHU 1.1, 1.2, & AHU 1.4

Skin

  • Marble installation continues on MC # 9, 10, & 11 (master climber).

HSRB – I Vivarium Expansion:

  • Installation of Overhead MEP lines and wall framing continues.

  • Rough – in of In-wall MEP continues.

  • Hang & Finish drywall.

  • Tie ins of utilities from HSRB – I expansion continues.

Site:

  • Selected finish grading in some areas.




11 views0 comments