top of page
  • Writer's pictureemoryhsrb2

Construction Update - 6/17/2022


This past week's (6/13/22 to 6/18/22) scheduled work activities:

G2

  • Office Furniture Installation.

  • Cyclotron Lead & door operator installation.

  • Installation of casework and benches continues.

  • Installation of vinyl plank flooring is underway.

G1

  • Office Furniture Installation.

  • Ceiling grid installation in 3T MRI suite.

  • Door installation continues.

  • Begin Terrazzo Flooring.

  • Installation of building vacuum pumps underway

Level 1

  • Operable Smoke evacuation panel installation continues.

  • Café' Rough in continues.

  • Installation of "liquid light" detail at L1 monumental stairs underway.

Level 2

  • L 2 North wing punch walk of rooms.

  • Stairwell drywall finishing continues.

  • Hanging drywall in East connector bridge to HSRB- I.

Level 3

  • Electrical trim out continues.

  • Symphony bench Installation continues in wet labs.

  • Installation of 9 wood ceilings continues

Level 4

  • Plumbing Fixture Installation.

  • Fire Alarm & Electrical device trim out continues various locations.

Level 5

  • Atrium soffit hanging drywall continues.

  • Lighting fixture installation.

Level 6

  • ACT Ceiling installation continues

  • Glass handrail installation continues.

  • Atrium soffit hanging continues.

  • Work continues on balcony ceilings and marble.

Mechanical Penthouse

  • Installation of Terracotta tiles on exterior of mechanical penthouses continues.

  • Installation of metal panels on the interior and exterior parapet walls continues.

  • TPO & mod- bit roof installation continues.

  • Building plenums & installing louvers.

Skin:

  • Installation of granite continues on the South elevation of building continues.

  • Installation of Rosa Borba & Marble at SW Entry is underway again.

  • Marble at balconies on North elevation continues.

HSRB – I Vivarium Expansion:

  • Installation of ceiling tiles.

  • Installation of utility connections to HSRB – I continue.

Site:

  • Installation concrete pathways on plaza level continues.

  • Light weight soil installation to continues.

  • Installation of two 15,000 gallon rain water cisterns has begun.

Next week's (6/20/22 to 6/25/22) scheduled work activities:

G2

  • G2 Level is going 100% clean booties must be worn at all times.

  • Final touch up painting underway.

  • SAT (site acceptance testing) begins for bio-repository.

G1

  • 7-T MRI calibration begins.

  • Ceiling grid installation in 3 T MRI suite begins.

  • Door installation continues.

  • Lighting fixtures in Mechanical rooms continues.

  • Continue installation of terrazzo flooring.

  • Door installation continues.

Level 1

  • Café MEP rough in continues.

  • Operable Smoke panel installation continues.

  • Punch walk of L 1 South.

Level 2

  • Stairwell drywall Finishing.

  • Hanging drywall in East connector with HSRB – I.

  • Atrium "liquid light " installation to continue.

Level 3

  • Electrical trim out continues.

  • Symphony bench installation continues.

Level 4

  • Fire alarm and electrical device trim out to continues.

  • Plumbing fixture installation continues.

Level 5

  • Hanging drywall in the atrium.

  • Light fixture installation.

Level 6

  • Installation of drywall ceiling in atrium continues.

  • Installation on balcony fascia continues.

  • ACT ceiling installation continues.

Mechanical Penthouse

  • Interior and exterior parapet metal panel installation continues.

  • Terra Cotta Installation on North & South Penthouse continues.

  • Mod – bit & TPO roof installation continues.

  • Building Plenums and Louver Installation to continue.

  • Outside air duct Installation.

Skin

  • Granite installation at South elevations continues.

  • Installation of marble at balconies continues.

  • installation Rosa Borba at SW Entry/elevation to continue.

HSRB – I Vivarium Expansion:

  • Ceiling tile installation to begin.

Site:

  • Rain water cistern excavation and installation to continue.

  • Side walk installation at East Plaza to continue.

  • LW soil installation to continue.



69 views0 comments

Recent Posts

See All
bottom of page