This past week's (6/13/22 to 6/18/22) scheduled work activities:
G2
Office Furniture Installation.
Cyclotron Lead & door operator installation.
Installation of casework and benches continues.
Installation of vinyl plank flooring is underway.
G1
Office Furniture Installation.
Ceiling grid installation in 3T MRI suite.
Door installation continues.
Begin Terrazzo Flooring.
Installation of building vacuum pumps underway
Level 1
Operable Smoke evacuation panel installation continues.
Café' Rough in continues.
Installation of "liquid light" detail at L1 monumental stairs underway.
Level 2
L 2 North wing punch walk of rooms.
Stairwell drywall finishing continues.
Hanging drywall in East connector bridge to HSRB- I.
Level 3
Electrical trim out continues.
Symphony bench Installation continues in wet labs.
Installation of 9 wood ceilings continues
Level 4
Plumbing Fixture Installation.
Fire Alarm & Electrical device trim out continues various locations.
Level 5
Atrium soffit hanging drywall continues.
Lighting fixture installation.
Level 6
ACT Ceiling installation continues
Glass handrail installation continues.
Atrium soffit hanging continues.
Work continues on balcony ceilings and marble.
Mechanical Penthouse
Installation of Terracotta tiles on exterior of mechanical penthouses continues.
Installation of metal panels on the interior and exterior parapet walls continues.
TPO & mod- bit roof installation continues.
Building plenums & installing louvers.
Skin:
Installation of granite continues on the South elevation of building continues.
Installation of Rosa Borba & Marble at SW Entry is underway again.
Marble at balconies on North elevation continues.
HSRB – I Vivarium Expansion:
Installation of ceiling tiles.
Installation of utility connections to HSRB – I continue.
Site:
Installation concrete pathways on plaza level continues.
Light weight soil installation to continues.
Installation of two 15,000 gallon rain water cisterns has begun.
Next week's (6/20/22 to 6/25/22) scheduled work activities:
G2
G2 Level is going 100% clean booties must be worn at all times.
Final touch up painting underway.
SAT (site acceptance testing) begins for bio-repository.
G1
7-T MRI calibration begins.
Ceiling grid installation in 3 T MRI suite begins.
Door installation continues.
Lighting fixtures in Mechanical rooms continues.
Continue installation of terrazzo flooring.
Door installation continues.
Level 1
Café MEP rough in continues.
Operable Smoke panel installation continues.
Punch walk of L 1 South.
Level 2
Stairwell drywall Finishing.
Hanging drywall in East connector with HSRB – I.
Atrium "liquid light " installation to continue.
Level 3
Electrical trim out continues.
Symphony bench installation continues.
Level 4
Fire alarm and electrical device trim out to continues.
Plumbing fixture installation continues.
Level 5
Hanging drywall in the atrium.
Light fixture installation.
Level 6
Installation of drywall ceiling in atrium continues.
Installation on balcony fascia continues.
ACT ceiling installation continues.
Mechanical Penthouse
Interior and exterior parapet metal panel installation continues.
Terra Cotta Installation on North & South Penthouse continues.
Mod – bit & TPO roof installation continues.
Building Plenums and Louver Installation to continue.
Outside air duct Installation.
Skin
Granite installation at South elevations continues.
Installation of marble at balconies continues.
installation Rosa Borba at SW Entry/elevation to continue.
HSRB – I Vivarium Expansion:
Ceiling tile installation to begin.
Site:
Rain water cistern excavation and installation to continue.
Side walk installation at East Plaza to continue.
LW soil installation to continue.