This past week's (5/23/22 to 5/28/22) scheduled work activities:
G2
Installation of toilet partitions.
Installation of Cyclotron continues
Installation of Biorepository nearing completion.
Organic Synthetic Chemistry lab casework install near completion.
G1
Trim out continues in BSL 3 areas.
3 T MRI drywall and wall finishing underway.
MEP rough in continues in 3 T suite.
Techniplast installation in aquatics suite continues.
Installation of case work continues various locations.
Level 1
Structural and wall framing continues in Café area.
MEP rough in at Café in early stages of installation.
Lab tables and bench installation continues.
Terrazzo floor and casework installation underway on L1 North.
Level 2
Lab Table and Bench installation continues.
Glass handrail installation continues.
9wood ceiling installation continues.
Level 3
Atrium soffit framing continues.
Installation of flooring in North wing offices.
Final coats of paint underway.
Installation of 9wood ceilings continues.
Installation of furnishing continues in write up areas.
Level 4
Atrium drywall soffit hanging continues.
Device trim out continues.
Level 5
Sterilizer MEP connections continue.
Lab casework installation continues.
Level 6
Installation of Interior storefront glass underway.
Final Coat paint – doors and frames.
ACT device trim out underway..
Mechanical Penthouse
Installation of Terracotta tiles on exterior of mechanical penthouses continues.
Installation of metal panels on the interior and exterior parapet walls continues.
TPO & mod- bit roof installation continues.
Installation of East Trellis continues.
Installation of HVAC Louvers & Dampers continues.
Installation of penthouse floor traffic coating underway.
Skin:
Installation of granite continues on the North and South elevation of building.
Installation of Rosa Borba& Marble at SW Entry continues.
Installation of marble & ceilings at North elevation balcony's continues .
HSRB – I Vivarium Expansion:
Installation of ACT grid underway.
Installation of utility connections to HSRB – I continue.
Site:
Installation of trees on plaza level continues.
Installation of additional cellular concrete on plaza is underway.
CW 1 scaffolding removal underway.
Light weight soil installation to continue.
Next week's (5/30/22 to 6/04/22) scheduled work activities:
G2
Stonehard installation to resume in select areas.
G1
7-T suite build out to continue.
7-T MRI drywall hanging and finishing to continue.
Stonehard installation resumes in selected areas.
BSL trim out to continue.
Plumbing fixture and bathroom accessory installation.
Level 1
Café MEP rough in to continue.
Level 1 North Owner punch.
Level 2
Installation of 9 2 wood ceilings to continue.
Lab table installation to continue.
Level 3
Installation of Flooring in North Offices.
Installation of 9wood ceilings continue..
Atrium Soffit finishing.
Level 4
Atrium soffit framing to continue.
Device trim out to continue.
Final coats of paint being applied.
Level 5
Sterilizer MEP connections continue.
Lab case work installation continues.
Atrium soffit framing continues.
Level 6
Interior store front glass installation continues.
Installation of glass handrailing's underway.
ACT device out continues
Mechanical Penthouse
Interior and exterior parapet metal panel installation continues.
Terra Cotta Installation on North & South Penthouse continues.
Mod – bit & TPO roof installation continues.
Louver Installation to continue.
AHU damper installation continues.
Traffic coat installation on floors continues.
Skin
Marble installation continues on MC 11, & 12 (master climber).
Granite installation at North elevation (balcony's) continues.
Installation of Rosa Borba on holding awaiting next shipment from Port of Savannah.
Granite installation at North & South elevations to continue.
HSRB – I Vivarium Expansion:
Stonehard installation to resume.
Site:
Cellular concrete installation at plaza level to continue.
Side walk layout prep at East Plaza to continue.
LW soil installation to continue
Comments