This past week's (6/06/22 to 6/11/22) scheduled work activities:
G2
Radiation Testing- Hot Cell/Cyclotron Systems.
Stonehard Floor Installation Completes.
G1
7 T MRI Helium Fill Begins.
Stonehard Floor Installation Completes.
Hang Dry wall in in 3 T MRI suite.
BSL exhaust diffuser installation completes.
Plumbing fixture installation.
Installation of tanks in aquatics suite.
Level 1
L 1 owner punch has begun.
Installation of operable panel has begun.
Café electrical rough in nearing completion.
East Plaza trellis completed.
Installation of Symphony benches continues
Level 2
Lab Table and Bench installation continues.
Finish drywall installation in connector.
Level 3
9 wood ceiling installation continues.
Framing of Green Wall structure continues on multiple floors.
Level 4
Atrium Soffit finishing.
Hanging drywall in the connector.
Device trim out continues various locations.
Level 5
Atrium soffit hanging drywall.
Install silicone on perimeter interior frames.
Level 6
Interior Storefront glass installation continues.
Glass handrail installation continues.
Atrium soffit hanging continues.
Work continues on balcony ceilings and marble.
Installation of fixed case work in wet labs continues.
Mechanical Penthouse
Installation of Terracotta tiles on exterior of mechanical penthouses continues.
Installation of metal panels on the interior and exterior parapet walls continues.
TPO & mod- bit roof installation continues.
Building plenums & installing louvers.
Skin:
Installation of granite continues on the North and South elevation of building continues.
Installation of Rosa Borba & Marble at SW Entry to begin again now that marble has arrived on site.
Marble at balconies on North elevation continues.
HSRB – I Vivarium Expansion:
Installation Stonehard continues.
Installation of utility connections to HSRB – I continue.
Site:
Installation concrete pathways on plaza level continues.
Light weight soil installation to continue.
Next week's (6/13/22 to 6/18/22) scheduled work activities:
G2
Site acceptance testing for the biorepository to begin.
G1
7-T MRI calibration begins.
Ceiling grid installation in 3 T MRI suite begins.
Door installation continues.
Lighting fixtures in Mechanical rooms continues.
Level 1
Café MEP rough in continues.
Operable panel installation continues.
Level 2
Stairwell drywall Finishing.
Hanging drywall in East connector with HSRB – I..
Atrium "liquid light " installation underway.
Level 3
Electrical trim out continues.
Symphony bench installation continues.
Level 4
Fire alarm and electrical device trim out to continues.
Plumbing fixture installation continues.
Level 5
Hanging drywall in the atrium.
Light fixture installation.
Level 6
Installation on balcony fascia continues.
ACT ceiling installation continues.
Mechanical Penthouse
Interior and exterior parapet metal panel installation continues.
Terra Cotta Installation on North & South Penthouse continues.
Mod – bit & TPO roof installation continues.
Building Plenums and Louver Installation to continue.
Outside air duct Installation.
Skin
Granite installation at North & South elevations continues.
Installation of marble at balconies continues.
Granite installation at North & South elevations to continue.
HSRB – I Vivarium Expansion:
Ceiling tile installation to begin.
Site:
Rain water cistern excavation and installation to begin.
Side walk installation at East Plaza to be completed.
LW soil installation to continue