Construction Update - 6/10/2022


This past week's (6/06/22 to 6/11/22) scheduled work activities:

G2

  • Radiation Testing- Hot Cell/Cyclotron Systems.

  • Stonehard Floor Installation Completes.

G1

  • 7 T MRI Helium Fill Begins.

  • Stonehard Floor Installation Completes.

  • Hang Dry wall in in 3 T MRI suite.

  • BSL exhaust diffuser installation completes.

  • Plumbing fixture installation.

  • Installation of tanks in aquatics suite.

Level 1

  • L 1 owner punch has begun.

  • Installation of operable panel has begun.

  • Café electrical rough in nearing completion.

  • East Plaza trellis completed.

  • Installation of Symphony benches continues

Level 2

  • Lab Table and Bench installation continues.

  • Finish drywall installation in connector.

Level 3

  • 9 wood ceiling installation continues.

  • Framing of Green Wall structure continues on multiple floors.

Level 4

  • Atrium Soffit finishing.

  • Hanging drywall in the connector.

  • Device trim out continues various locations.

Level 5

  • Atrium soffit hanging drywall.

  • Install silicone on perimeter interior frames.

Level 6

  • Interior Storefront glass installation continues.

  • Glass handrail installation continues.

  • Atrium soffit hanging continues.

  • Work continues on balcony ceilings and marble.

  • Installation of fixed case work in wet labs continues.

Mechanical Penthouse

  • Installation of Terracotta tiles on exterior of mechanical penthouses continues.

  • Installation of metal panels on the interior and exterior parapet walls continues.

  • TPO & mod- bit roof installation continues.

  • Building plenums & installing louvers.

Skin:

  • Installation of granite continues on the North and South elevation of building continues.

  • Installation of Rosa Borba & Marble at SW Entry to begin again now that marble has arrived on site.

  • Marble at balconies on North elevation continues.

HSRB – I Vivarium Expansion:

  • Installation Stonehard continues.

  • Installation of utility connections to HSRB – I continue.

Site:

  • Installation concrete pathways on plaza level continues.

  • Light weight soil installation to continue.

Next week's (6/13/22 to 6/18/22) scheduled work activities:

G2

  • Site acceptance testing for the biorepository to begin.

G1

  • 7-T MRI calibration begins.

  • Ceiling grid installation in 3 T MRI suite begins.

  • Door installation continues.

  • Lighting fixtures in Mechanical rooms continues.

Level 1

  • Café MEP rough in continues.

  • Operable panel installation continues.

Level 2

  • Stairwell drywall Finishing.

  • Hanging drywall in East connector with HSRB – I..

  • Atrium "liquid light " installation underway.

Level 3

  • Electrical trim out continues.

  • Symphony bench installation continues.

Level 4

  • Fire alarm and electrical device trim out to continues.

  • Plumbing fixture installation continues.

Level 5

  • Hanging drywall in the atrium.

  • Light fixture installation.

Level 6

  • Installation on balcony fascia continues.

  • ACT ceiling installation continues.

Mechanical Penthouse

  • Interior and exterior parapet metal panel installation continues.

  • Terra Cotta Installation on North & South Penthouse continues.

  • Mod – bit & TPO roof installation continues.

  • Building Plenums and Louver Installation to continue.

  • Outside air duct Installation.

Skin

  • Granite installation at North & South elevations continues.

  • Installation of marble at balconies continues.

  • Granite installation at North & South elevations to continue.

HSRB – I Vivarium Expansion:

  • Ceiling tile installation to begin.

Site:

  • Rain water cistern excavation and installation to begin.

  • Side walk installation at East Plaza to be completed.

  • LW soil installation to continue