Construction Update - 5/20/2022


This past week's (5/16/22 to 5/21/22) scheduled work activities:

G2

  • Installation of lab casework benches

  • Installation of Cyclotron continues

  • Device trim out continues.

G1

  • Trim out continues in BSL 3 areas.

  • Work in 7 T suite build out continues after successful delivery.MEP rough in continues in 3 T suite.

  • Techniplast installation in aquatics suite continues.

  • Installation of case work continues various locations.

Level 1

  • Structural and wall framing continues in Café area.

  • Installation of case work continues various locations.

Level 2

  • Atrium Soffit Drywall work finishing.

  • Atrium Glass handrailing's installation underway.

  • Installation of 9 wood ceilings continues.

  • Installation of carpet continues in various locations

Level 3

  • Final coat of paint continues.

  • Monumental stair framing underway continues.

  • Carpet installation in North Offices has underway.

  • Installation of selected mill work has begun

Level 4

  • Atrium drywall soffit hanging underway.

  • Device trim out continues.

Level 5

  • Sterilizer MEP connections continue

  • Interior atrium glass and handrailing installation continues.

  • Lab casework installation continues.

  • Interior store front glass installation continues

Level 6

  • Atrium Soffit framing continues.

  • Final Coat paint – doors and frames.

  • ACT device trim out underway.

Mechanical Penthouse

  • Installation of Terracotta tiles on exterior of mechanical penthouses continues.

  • Installation of metal panels on the interior and exterior parapet walls continues.

  • TPO & mod- bit roof installation continues.

  • Installation of East Trellis continues.

  • Installation of HVAC Louvers continues.

Skin:

  • Marble installation continues on South & SW Façade of South Tower @ MC 11 & #12.

  • Installation of granite continues on the North and South elevation of building.

  • Installation of Rosa Borba at SW Entry continues.

  • Installation of marble & ceilings at North elevation balcony's continues .

HSRB – I Vivarium Expansion:

  • Installation of ACT grid underway.

  • Installation of utility connections to HSRB – I continue.

Site:

  • Installation of trees on plaza level continues.

  • Installation of additional cellular concrete on plaza is underway.

Next week's (5/23/22 to 5/28/22) scheduled work activities:

G2

  • Toilet partition installation to begin.

G1

  • 7-T suite build out to continue.

  • 7-T MRI drywall hanging and finishing to continue.

  • 3-T MRI MEP rough in to complete.

  • BSL trim out to continue.

Level 1

  • Café MEP rough in to continue.

  • Lab Tables and bench installation to continue.

Level 2

  • Installation of 9 2 wood ceilings to continue.

  • Lab table installation to continue.

  • Glass handrail installation to continue.

Level 3

  • Installation of Flooring in North Offices.

  • Final paint coat to be applied.

  • Atrium Soffit finishing

Level 4

  • Atrium soffit framing to continue.

  • Device trim out to continue.

Level 5

  • Sterilizer MEP connections continue.

  • Lab case work installation continues.

Level 6

  • Interior store front glass installation.

  • Final coat of paint doors and frames.

  • ACT device out continues

Mechanical Penthouse

  • Interior and exterior parapet metal panel installation continues.

  • Terra Cotta Installation on North & South Penthouse continues.

  • Mod – bit & TPO roof installation continues.

  • East Trellis installation to continue.

  • Louver Installation to continue.

  • AHU damper installation to begin.

  • Traffic coat installation on floors continues

Skin

  • Marble installation continues on MC 11, & 12 (master climber).

  • Granite installation at North elevation (balcony's) continues.

  • Installation of Rosa Borba to continue.

  • Granite installation at North & South elevations to continue.

HSRB – I Vivarium Expansion:

  • ACT ceiling grid installation to continue.

Site:

  • Cellular concrete installation at plaza level to continue.

  • Side walk layout prep at East Plaza to begin.

  • LW soil installation to continue