This past week's (5/16/22 to 5/21/22) scheduled work activities:
G2
Installation of lab casework benches
Installation of Cyclotron continues
Device trim out continues.
G1
Trim out continues in BSL 3 areas.
Work in 7 T suite build out continues after successful delivery.MEP rough in continues in 3 T suite.
Techniplast installation in aquatics suite continues.
Installation of case work continues various locations.
Level 1
Structural and wall framing continues in Café area.
Installation of case work continues various locations.
Level 2
Atrium Soffit Drywall work finishing.
Atrium Glass handrailing's installation underway.
Installation of 9 wood ceilings continues.
Installation of carpet continues in various locations
Level 3
Final coat of paint continues.
Monumental stair framing underway continues.
Carpet installation in North Offices has underway.
Installation of selected mill work has begun
Level 4
Atrium drywall soffit hanging underway.
Device trim out continues.
Level 5
Sterilizer MEP connections continue
Interior atrium glass and handrailing installation continues.
Lab casework installation continues.
Interior store front glass installation continues
Level 6
Atrium Soffit framing continues.
Final Coat paint – doors and frames.
ACT device trim out underway.
Mechanical Penthouse
Installation of Terracotta tiles on exterior of mechanical penthouses continues.
Installation of metal panels on the interior and exterior parapet walls continues.
TPO & mod- bit roof installation continues.
Installation of East Trellis continues.
Installation of HVAC Louvers continues.
Skin:
Marble installation continues on South & SW Façade of South Tower @ MC 11 & #12.
Installation of granite continues on the North and South elevation of building.
Installation of Rosa Borba at SW Entry continues.
Installation of marble & ceilings at North elevation balcony's continues .
HSRB – I Vivarium Expansion:
Installation of ACT grid underway.
Installation of utility connections to HSRB – I continue.
Site:
Installation of trees on plaza level continues.
Installation of additional cellular concrete on plaza is underway.
Next week's (5/23/22 to 5/28/22) scheduled work activities:
G2
Toilet partition installation to begin.
G1
7-T suite build out to continue.
7-T MRI drywall hanging and finishing to continue.
3-T MRI MEP rough in to complete.
BSL trim out to continue.
Level 1
Café MEP rough in to continue.
Lab Tables and bench installation to continue.
Level 2
Installation of 9 2 wood ceilings to continue.
Lab table installation to continue.
Glass handrail installation to continue.
Level 3
Installation of Flooring in North Offices.
Final paint coat to be applied.
Atrium Soffit finishing
Level 4
Atrium soffit framing to continue.
Device trim out to continue.
Level 5
Sterilizer MEP connections continue.
Lab case work installation continues.
Level 6
Interior store front glass installation.
Final coat of paint doors and frames.
ACT device out continues
Mechanical Penthouse
Interior and exterior parapet metal panel installation continues.
Terra Cotta Installation on North & South Penthouse continues.
Mod – bit & TPO roof installation continues.
East Trellis installation to continue.
Louver Installation to continue.
AHU damper installation to begin.
Traffic coat installation on floors continues
Skin
Marble installation continues on MC 11, & 12 (master climber).
Granite installation at North elevation (balcony's) continues.
Installation of Rosa Borba to continue.
Granite installation at North & South elevations to continue.
HSRB – I Vivarium Expansion:
ACT ceiling grid installation to continue.
Site:
Cellular concrete installation at plaza level to continue.
Side walk layout prep at East Plaza to begin.
LW soil installation to continue