This past week's (2/14/22 to 2/19/22) scheduled work activities:
G2
Installation of Bathroom Tile has been completed.
Installation of Biorepository continues.
G1
Stonhard installation in BSL3 labs North & South continues.
Installation of fixtures in bathrooms underway.
Framing of walls and ceiling in G1 West Lobby continues.
Installation of Stainless Steel casework in Vivarium continues.
Installation of MRI Quench Vent
Level 1
Fume hood installation underway in South Tower Wet Labs.
Installation of Center monumental stairs is underway.
Framing of center atrium ceiling and soffits underway.
Level 2
Installation of Interior storefront glass installation continues on L1 & L2
West atrium soffit continues.
Level 3
Installation of interior store front glass continues.
Installation of doors and glass sidelights continues at offices.
Progress view from L3 West bridge looking East into Atrium area towards HSRB-I (2/17/21 Versus 2/17/22)
Level 4
Terminate lab panels.
Atrium electrical rough-in begins.
Lab light fixture & Service panel installation continues in South Tower wet labs.
Finishing of drywall in South Tower continues.
Level 5
Installation/hanging of Drywall in North Tower Underway.
Installation of lighting & service panels in South Labs continues.
Level 6
Drywall installation completed at interior of Skylight.
In wall MEP Rough-in continues.
Mechanical Penthouse
Installation of Terracotta tiles on exterior of mechanical penthouses has begun.
Exterior Eyebrow metal panels is underway at MC 3 & 4.
Air Handling Units (AHU) device installation continues.
TPO roof installation continues on the South Penthouse roof.
Final coat of colored stucco at exterior skylight walls is in progress.
Skin:
HSRB – I Vivarium Expansion:
Installation of overhead MEP pipes continues.
Framing of walls in interior of space continues.
HVAC ductwork pressure testing is underway.
Site:
Installation of light weight soils for plaza areas continues.
Next week's (2/21/22 to 2/26/22) scheduled work activities:
G2
Installation of Biorepository to continue.
Final coat of paint applied in offices.
Biorepository installation continues.
G1
Installation of Stonhard in BSL 3 labs to be completed.
Drywall and framing continues throughout space.
Framing of walls and ceilings in G1 Lobby continues
Stainless Steel Countertops in Vivarium continues.
Installation of ACT grid to continue in South Tower.
Level 1
Sterilizer installation begins.
installation of lab casework resumes.
Hanging of walls in granting garden continues.
Installation of Fume Hood Alcoves continues.
Level 2
Installation of Fixed casework continues
Sterilizer installation begins.
Installation of Atrium window wall framing.
Level 3
Sterilizer installation begins.
Primer & first coat of paint in South Labs.
Level 4
Sterilizer installation begins.
Terminate lab panels.
Finishing of Drywall in – South Tower continues.
Atrium electrical rough-in continues.
Level 5
Finishing of Drywall in North Tower is underway.
Hanging of Drywall in South Tower continues.
Level 6:.
In wall MEP rough - ins continues.
Mechanical Penthouse
Skin
Marble installation continues on MC # 9, 10, & 12 (master climber).
Installation of MRI Quench vent has begun.
HSRB – I Vivarium Expansion:
Installation of Overhead MEP lines and wall framing continues.
Rough – in of In-wall MEP continues.
Top out of Drywall begins.
Site:
Installation of conduit and plaza area light bases continues.
Excavation for North courtyard continues.
Commentaires