This past week's (2/07/22 to 2/12/22) scheduled work activities:
G2
Fume Hood installation
Installation of lighting in Hot cell area.
G1
Stonhard installation in BSL3 labs North & South continues.
Installation of stainless steel counter tops begins in Vivarium.
Drywall framing & finishing continues in various areas.
Framing of walls and ceiling in G1 Lobby continues.
Work on G1 restrooms continue.
Level 1
Fume hood installation underway in South Tower Wet Labs.
Painting of Hard ceilings in L1 south labs and installation of can lights continues.
West Atrium walls & soffit framing continues.
Installation of drywall in Central atrium area continues.
Installation of flooring continues on L1 South
Level 2
Installation of Interior storefront glass installation continues on L1 & L2
ACT Ceiling grid and Rough-in continues and North tower offices continues.
Level 3
Installation of interior store front glass continues.
Installation of doors and glass sidelights continues at offices.
Level 4
Lab light fixture & Service panel installation continues in South Tower wet labs.
Finishing drywall in South Tower.
Level 5
Installation of Drywall in South Tower continues.
Installation of lighting & service panels in South Labs.
Level 6
Drywall installation at interior of Skylight continues
In wall MEP Rough-in continues.
Mechanical Penthouse
Installation of TPO roofing on South Penthouse roof continues.
Air Handling Units (AHU) device installation continues
Skin:
HSRB – I Vivarium Expansion:
Installation of overhead MEP pipes continues.
Framing of walls in interior of space has begun
Cutting doorway into HRB – I vivarium level has begun.
Site:
Installation of light weight soils for plaza areas continues.
Next week's (2/14/22 to 2/19/22) scheduled work activities:
G2
Installation of Biorepository to continue.
Bathroom Tile installation to finish.
G1
Installation of Stonhard in BSL 3 labs continue.
Drywall and framing continues throughout space.
Framing of walls and ceilings in G1 Lobby continues
Stainless Steel Countertops in Vivarium continues.
Catwalk MEP work continues.
Level 1
Drywall & Framing continues throughout area.
Installation of center monumental stairs continues.
Level 2
Atrium window wall installation continues.
West Atrium soffit framing continue.
Level 3
Installation of sidelight glass at North Offices continues.
Installation of interior storefront to continue.
Level 4
Terminate lab panels.
Finishing of Drywall in – South Tower continues.
Atrium electrical rough-in continues.
Level 5
Installation of lighting and service panels in Wet Labs continues.
Hanging of Drywall in South Tower continues.
Level 6:
Installation of drywall at Skylight scheduled to be completed.
In wall MEP rough - ins continues.
Mechanical Penthouse
Skin
Marble installation continues on MC # 9, 10, & 12 (master climber).
Installation of TPO roofing continues on South Penthouse Roof continues.
Structural Curtin wall #1 glass installation prep continues.
Final coat of stucco installed at Skylight exterior walls (weather permitting).
Curtainwall % & 6 installation at Ped. bridges continues.
HSRB – I Vivarium Expansion:
Installation of Overhead MEP lines and wall framing continues.
Site:
Installation of light weight soils continues.
Excavation for North courtyard continues.