This past week's (1/31/22 to 2/05/22) scheduled work activities:
G2
Biorepository Installation continues.
Installation of lighting in Hot cell area.
G1
Stonhard installation in BSL3 labs North & South continues.
Installation of plumbing fixtures in restrooms is underway
Drywall finishing in imaging center control rooms.
Wonder wall framing continues.
Framing of Vivarium Office walls continues.
Level 1
Interior store front Installation underway.
Installation of Fixed Casework and wall standards in wet labs.
Trimming out of electrical devices underway.
Level 2
Atrium soffit framing & electrical rough in underway.
Interior storefront glass installation continues.
ACT Ceiling grid and Rough-in continues.
Level 3
Finishing Drywall in North Tower.
Priming and first coat of paint South Tower.
Level 4
Finishing drywall South Tower.
Framing of West Atrium bridge.
Level 5
Installation of Drywall in South Tower.
Installation of electrical panels in South Labs
Level 6
Drywall installation at interior of Skylight.
In wall MEP Rough-in continues.
Mechanical Penthouse
Eyebrow framing on Master Climbers #5 & MC#6 continues.
AHU device installation continues.
Painting of fire sprinkler piping continues at underside of skylight.
Skin:
Installation of TPO roofing on South Penthouse roofs continues.
Structural curtainwall panting completed.
Stucco installation on exterior of Skylight has begun.
Curtain wall #6 installation continues.
West Trellis Installation has begun.
Installation of glass on East pedestrian bridges continues.
HSRB – I Vivarium Expansion:
Installation of overhead MEP pipes continues.
Framing of walls in interior of space has begun
Site:
Installation of light weight soils for plaza areas continues.
Next week's (2/07/22 to 2/12/22) scheduled work activities:
G2
Installation of Biorepository to continue.
Installation of Fume hoods begins.
G1
Installation of Stonhard in BSL 3 labs continue.
Drywall and drying continues throughout space.
Framing of ceilings inG1 Lobby.
Stainless Steel Countertops in Viv begins.
Level 1
Fume hood Installation in South Wet Labs.
Installation of center monumental stairs begins.
West Atrium Soffit Framing underway.
Level 2
Interior Storefront installation continues.
West Atrium soffit framing.
Level 3
Installation of Glass at North Offices.
Installation of interior storefront to continue.
Level 4
Lab Lighting and Service panel installation continues.
Hanging Drywall in – South Tower continues.
Level 5
Installation of lighting and service panels in Wet Labs continues.
Hanging of Drywall in South Tower.
Level 6:
Installation of drywall at Skylight contnues.
In wall MEP rough - ins continues,
Mechanical Penthouse
Skin
Marble installation continues on MC # 8, 9, & 10 (master climber).
Installation of TPO roofing continues on South Penthouse Roof continues.
Structural Curtin wall #1 glass installation prep continues.
Stucco installation at Skylight exterior continues (weather permitting).
Curtainwall 6 installation continues.
HSRB – I Vivarium Expansion:
Installation of Overhead MEP lines continues and wall framing.
Site:
Installation of light weight soils continues.
Excavation for North courtyard continues.
Comments