This past week's (4/25/22 to 4/30/22) scheduled work activities:
G2
Installation of ceiling tiles.
G1
Installation of ceiling grid in Aquatics Suite
7T Electrical Equipment installation continues.
Final coat being applied in offices.
7T MRI Suite RF Shielding and wall build out continues.
Installation of 7 T ceiling grid
Dry wall Installation and finishing continues.
Level 1
9 wood ceiling installation in corridors has begun.
Furniture installation has begun on L1.
Installation and finishing of hard/drywall ceilings continues.
Level 2
Installation at Balconet fascia underway.
Application of final coat of paint underway.
Installation of Carpet and cove base underway.
Level 3
Framing of exterior balcony ceilings underway.
Lab casework counter installation continues.
Level 4
Mechanical connections to sterilizers continues.
Installation of Atrium drywall and framing continues.
Installation of casework in meeting rooms continues.
Level 5
Framing of the Monumental Stairs continues.
Installation of hard ceilings in meeting space. underway.
Installation of light fixtures in hard ceilings.
Framing of ceilings in atrium continues.
Level 6
Eyebrow drain installation continues
Installation of glass handrailing shoes on East Monumental stairs.
Hanging hard ceilings
Work on Skylight continues.
Application of primer and 1st coat of finish paint underway.
Mechanical Penthouse
Installation of Terracotta tiles on exterior of mechanical penthouses continues.
Installation of metal panels on the interior and exterior parapet walls continues.
TPO & mod- bit roof installation continues.
Installation of East Trellis continues
Skin:
HSRB – I Vivarium Expansion:
Stonhard installation is underway.
Installation of utility connections to HSRB – I continue.
Site:
Installation of trees on plaza level continues.
Next week's (5/02/22 to 5/07/22) scheduled work activities:
G2
Installation of Lab casework and benches.
G1
Installing ceiling grid in G1 Lobby.
Installing ceiling tile in BSL 3 labs.
7 T MEP overhead rough in underway.
Techniplast delivery in aquatics and installation
Level 1
Installation of light fixtures in 9 wood ceilings.
Lab Tables and bench installation to begin
Level 2
Plumbing fixture installation underway.
Application of Final coat of paint underway.
Installation of 9 wood ceilings to begin.
Level 3
Finish installation of Canopy hoods.
Framing of monumental stairs to continue.
Level 4
Startup of Phoenix valves.
Installation of Lab casework continues.
Dropping of ceiling tile in North and South Wings.
Level 5
Installation of lab casework continues.
ACT Grid installation continues – North Wing.
Atrium soffit framing continues.
Level 6:.
Installation of balcony glass is underway.
Lab casework delivery.
Mechanical Penthouse
Interior and exterior parapet metal panel installation continues.
Terra Cotta Installation on North & South Penthouse continues.
Mod – bit & TPO roof installation continues.
East Trellis installation begins.
Skin
Marble installation continues on MC # 7, 8, 11, & 12 (master climber).
Granite installation at North elevation continues.
Installation of Rosa Borba to continue.
HSRB – I Vivarium Expansion:
Installation of Stonehard in vivarium expansion to conclude.
Tie ins of utilities from HSRB – I expansion continues.
Site:
Selected finish grading in some areas.
Comments