This past week's (2/21/22 to 2/26/22) scheduled work activities:
G2
MEP connections to fume hoods underway.
Installation of Biorepository continues.
Final coat of paint in offices.
G1
Stonhard installation in BSL3 labs North & South nears completion.
7T MRI Slab remediation continues.
Framing of walls and ceiling in G1 West Lobby continues.
Installation of Stainless Steel casework in Vivarium continues.
Installation of monumental stairs from G1 to L1 has begun.
Level 1
Sterilizer Installation has begun
Installation of casework in wet labs has resumed.
Installation of drywall on granting garden wall has begun.
Level 2
Installation of Interior storefront frames & glass continues on L1 & L2
Installation of Fixed casework
Sterilizer Installation underway
Installation of ceiling grid in corridors and offices.
Level 3
Installation of interior store front glass continues.
Installation of doors and glass sidelights continues at offices.
Painting of wet labs drywall with primer & 1st coats of finish paint.
Installation of storefront frames in Atrium.
Level 4
Terminate lab panels.
Atrium electrical rough-in continues.
Lab light fixture & Service panel installation continues in South Tower wet labs.
Finishing of drywall in South Tower continues.
Level 5
Installation/hanging of Drywall in South Tower Underway.
Finishing of drywall in the North Tower.
Installation of lighting & service panels in South Labs continues.
Level 6
In wall MEP Rough-in continues.
Mechanical Penthouse
Installation of Terracotta tiles on exterior of mechanical penthouses continues.
Exterior Eyebrow metal panels is underway at MC 1 to 4.
Air Handling Units (AHU) device installation continues.
TPO roof installation continues on the South Penthouse roof.
Final coat of colored stucco at exterior skylight walls is in progress.
Installation of acoustical panels at interior of Skylight is 90% completed.
Skin:
HSRB – I Vivarium Expansion:
Installation of overhead MEP pipes continues.
Framing of walls in interior of space continues.
HVAC ductwork pressure testing is underway.
In wall MEP rough in underway.
Site:
Installation of light weight soils for plaza areas continues.
Next week's (2/28/22 to 3/05/22) scheduled work activities:
G2
Installation of Biorepository to continues.
MEP connection to fume hoods continues.
Installation of lab casework continues.
G1
7 T MRI lab remediation continues.
MEP Final connections continue.
Monumental stair installation continues.
Level 1
Casework installation resumes.
Hanging of granting garden wall begins.
Level 2
Installation of Fixed casework continues.
Installation of Atrium window wall framing continues.
Level 3
Sterilizer installation continues.
Primer & first coat of paint in South Labs.
Atrium storefront frame installation continues.
Level 4
Sterilizer installation continues.
Terminate lab panels.
Finishing of Drywall in – South Tower continues.
Atrium electrical rough-in continues.
Level 5
Finishing of Drywall in North Tower is underway.
Hanging of Drywall in South Tower continues.
Level 6:.
In wall MEP rough - ins continues.
Mechanical Penthouse
Skin
Marble installation continues on MC # 9, 10, & 12 (master climber).
Terracotta tile installation continues North penthouse.
HSRB – I Vivarium Expansion:
Installation of Overhead MEP lines and wall framing continues.
Rough – in of In-wall MEP continues.
Top out of Drywall continues.
Tie ins of utilities from HSRB – I expansion continues.
Site:
Installation of conduit and plaza area light bases continues.
Excavation for North courtyard continues.