top of page
Writer's pictureemoryhsrb2

Construction Update - 2/25/2022



This past week's (2/21/22 to 2/26/22) scheduled work activities:

G2

  • MEP connections to fume hoods underway.

  • Installation of Biorepository continues.

  • Final coat of paint in offices.

G1

  • Stonhard installation in BSL3 labs North & South nears completion.

  • 7T MRI Slab remediation continues.

  • Framing of walls and ceiling in G1 West Lobby continues.

  • Installation of Stainless Steel casework in Vivarium continues.

  • Installation of monumental stairs from G1 to L1 has begun.

Level 1

  • Sterilizer Installation has begun

  • Installation of casework in wet labs has resumed.

  • Installation of drywall on granting garden wall has begun.

Level 2

  • Installation of Interior storefront frames & glass continues on L1 & L2

  • Installation of Fixed casework

  • Sterilizer Installation underway

  • Installation of ceiling grid in corridors and offices.

Level 3

  • Installation of interior store front glass continues.

  • Installation of doors and glass sidelights continues at offices.

  • Painting of wet labs drywall with primer & 1st coats of finish paint.

  • Installation of storefront frames in Atrium.

Level 4

  • Terminate lab panels.

  • Atrium electrical rough-in continues.

  • Lab light fixture & Service panel installation continues in South Tower wet labs.

  • Finishing of drywall in South Tower continues.

Level 5

  • Installation/hanging of Drywall in South Tower Underway.

  • Finishing of drywall in the North Tower.

  • Installation of lighting & service panels in South Labs continues.

Level 6

  • In wall MEP Rough-in continues.

Mechanical Penthouse

  • Installation of Terracotta tiles on exterior of mechanical penthouses continues.

  • Exterior Eyebrow metal panels is underway at MC 1 to 4.

  • Air Handling Units (AHU) device installation continues.

  • TPO roof installation continues on the South Penthouse roof.

  • Final coat of colored stucco at exterior skylight walls is in progress.

  • Installation of acoustical panels at interior of Skylight is 90% completed.

Skin:

  • Marble installation continues on South & SW Façade of South Tower @ MC #9, #10 & #12.

  • Installation of curtainwall glass at Pedestrian bridges continues.

  • Installation on glass has begun at curtain wall #6.

HSRB – I Vivarium Expansion:

  • Installation of overhead MEP pipes continues.

  • Framing of walls in interior of space continues.

  • HVAC ductwork pressure testing is underway.

  • In wall MEP rough in underway.

Site:

  • Installation of light weight soils for plaza areas continues.

Next week's (2/28/22 to 3/05/22) scheduled work activities:

G2

  • Installation of Biorepository to continues.

  • MEP connection to fume hoods continues.

  • Installation of lab casework continues.

G1

  • 7 T MRI lab remediation continues.

  • MEP Final connections continue.

  • Monumental stair installation continues.

Level 1

  • Casework installation resumes.

  • Hanging of granting garden wall begins.

Level 2

  • Installation of Fixed casework continues.

  • Installation of Atrium window wall framing continues.

Level 3

  • Sterilizer installation continues.

  • Primer & first coat of paint in South Labs.

  • Atrium storefront frame installation continues.

Level 4

  • Sterilizer installation continues.

  • Terminate lab panels.

  • Finishing of Drywall in – South Tower continues.

  • Atrium electrical rough-in continues.

Level 5

  • Finishing of Drywall in North Tower is underway.

  • Hanging of Drywall in South Tower continues.

Level 6:.

  • In wall MEP rough - ins continues.

Mechanical Penthouse

  • Installation of Metal panels at Eyebrows above Master Climbers #1 to #4 to continue.

  • AHU device installation continues.

  • Installation of Terracotta tiles to continue.

  • Framing of Roof Doghouses continues.

Skin

  • Marble installation continues on MC # 9, 10, & 12 (master climber).

  • Terracotta tile installation continues North penthouse.

HSRB – I Vivarium Expansion:

  • Installation of Overhead MEP lines and wall framing continues.

  • Rough – in of In-wall MEP continues.

  • Top out of Drywall continues.

  • Tie ins of utilities from HSRB – I expansion continues.

Site:

  • Installation of conduit and plaza area light bases continues.

  • Excavation for North courtyard continues.



12 views0 comments

Recent Posts

See All

Commentaires


bottom of page