The traffic flow restrictions and lane reductions along Haygood Drive between Clifton and Ridgewood Drive that began on Tuesday 3/2/22 are the results of a DeKalb County Water line installation project.
This work is being managed by DeKalb County and not Emory's Planning, Design, and Construction Department.
We are told that weather permitting the project will take between 6 – 8 weeks and will be completed prior to Emory's Graduation weekend activities.
This past week's (3/28/22 to 4/02/22) scheduled work activities:
G2
Installation of breakroom millwork has begun.
Final trim out of Cyclotron has begun.
Interior Storefront Doors and Glass is underway.
G1
Installation of 7T shielding continues.
ACT ceiling framing and tile installation is underway.
Breakroom Millwork Installation is underway.
Vivarium device trim out continues.
Framing, drywalling, and finishing of ceiling at Wonder Wall is underway
Level 1
Terrazzo installation has begun in North wing.
ACT tile installation in North and South wings is underway.
Sterilizer Mod wall delivery L1-L6
Installation of Controlled Environmental rooms has begun.
Work continues at L1 down to G1 Lobby/Wonderwall area.
Level 2
Plumbing fixture installation continues.
Installation of glass atrium handrails is underway
Level 3
Tie in of the vent connects to Fume hoods continues.
Level 4
Resilient Flooring Installation started in South wing L4.
Installation of glass hand railings, in Center & West atrium continues.
Fixed casework & Counter Top Deliveries.
Level 5
Prime Paint continues in North wing .
Hanging Drywall ceilings North wing.
Level 6
Installation of trap primers continues.
Work continues on the interior of the skylight.
ACM installation at exterior "eyebrow" continues.
Mechanical Penthouse
Installation of Terracotta tiles on exterior of mechanical penthouses continues.
Installation of metal panels on the interior and exterior parapet walls continues.
TPO & mod- bit roof installation continues.
Skin:
HSRB – I Vivarium Expansion:
Installation of overhead MEP continues.
In wall MEP rough in continues.
Installation of utility connections to HSRB – I are underway.
Installation of Drywall continues in select areas.
Site:
Installation of trees on plaza level continues.
Next week's (4/04/22 to 4/09/22) scheduled work activities:
G2
Installation of Biorepository to continues.
Wood Door installation continues.
GE to continue of the cyclotron installation.
Breakroom tile backsplash.
G1
Installation of Stair #4 continues South East Corner of South wing.
FRP door installation in BSL areas continues.
Vivarium device trim out continues
Monumental stair installation continues. G1 to L1
7T equipment cabinets delivery.
Level 1
Fixture and Device trim out continues.
Installation of accessories in restrooms continues.
Millwork cabinetry Installation.
Carpet installation in North Offices.
Level 2
ACT ceiling tile installation continues.
Installation of interior glass store front doors and windows continues.
Level 3
Installation of Glass Hand railings – center atrium.
Plumbing fixture installation continues.
Level 4
Installation of glass handrails – center atrium continues.
ACT framing continues North Wing.
Level 5
South wing ACT ceiling rough-in.
Finishing drywall ceilings.
Level 6:.
ACM installation continues at the Eyebrow.
Finishing dry wall – South Wing.
Mechanical Penthouse
Interior and exterior parapet metal panel installation continues.
Terra Cotta Installation on North & South Penthouse continues.
Mod – bit & TPO roof installation continues.
Skin
Marble installation continues on MC # 9, 10, & 11 (master climber).
Granite installation at West elevation continues.
HSRB – I Vivarium Expansion:
Installation of Overhead MEP lines and wall framing continues.
Rough – in of In-wall MEP continues.
Hang & Finish drywall.
Tie ins of utilities from HSRB – I expansion continues.
Site:
Selected finish grading in some areas.