This past week's (5/25/20 to 5/30/20) scheduled work activities:
G2 Level:
Spread footings and columns continue
Continuous footings and foundation walls continue
Backfilling SW corner
Dig and form areaway
Waterproofing of foundations continue
G1 Level:
Spread footings and columns continue
Continuous footings and foundation walls continue
Dig and form areaway
Waterproofing of foundations continue
Deep underground electrical duct bank at G1 West
Next week's (5/11/20 to 5/16/20) scheduled work activities:
G2 Level:
Pour Elevator 5 foundation
Plumbing Test & Inspection
Pour cyclotron walls
Service electrical duct bank to stub up at vault
G1 Level:
Spread footings and columns continue
Continuous footings & foundation walls continue
Waterproofing foundations continue
Deep underground electrical duct bank at G1 North