Construction Update - 5/29/2020


This past week's (5/25/20 to 5/30/20) scheduled work activities:


G2 Level:

  • Spread footings and columns continue

  • Continuous footings and foundation walls continue

  • Backfilling SW corner

  • Dig and form areaway

  • Waterproofing of foundations continue

G1 Level:

  • Spread footings and columns continue

  • Continuous footings and foundation walls continue

  • Dig and form areaway

  • Waterproofing of foundations continue

  • Deep underground electrical duct bank at G1 West

Next week's (5/11/20 to 5/16/20) scheduled work activities:


G2 Level:

  • Pour Elevator 5 foundation

  • Plumbing Test & Inspection

  • Pour cyclotron walls

  • Service electrical duct bank to stub up at vault

G1 Level:

  • Spread footings and columns continue

  • Continuous footings & foundation walls continue

  • Waterproofing foundations continue

  • Deep underground electrical duct bank at G1 North