Apr 20, 2021
Construction Update - 4/16/2021
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...
emoryhsrb2
Apr 20, 2021
Construction Update - 4/09/2021
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...
emoryhsrb2
Jul 7, 2020
Construction Update - 7/3/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...
emoryhsrb2
Jun 24, 2020
Construction Update - 6/5/2020
This past week's (6/1/20 to 6/6/20) scheduled work activities: G2 Level: Continuous footings & foundation walls continue Pour Elevator 5...
emoryhsrb2
Jun 24, 2020
Construction Update - 5/29/2020
This past week's (5/25/20 to 5/30/20) scheduled work activities: G2 Level: Spread footings and columns continue Continuous footings and...
emoryhsrb2
Jun 24, 2020
Construction Update - 5/22/2020
This past week's (5/18/20 to 5/23/20) scheduled work activities: Pour elevator 5 foundation at G-2 Level. Pour pile caps at G-2 level A...
emoryhsrb2
May 13, 2020
Construction Update - 5/1/2020
The HSRB–II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...
emoryhsrb2
Apr 24, 2020
Construction Update- 4/24/2020
This past week's (4/20/20 to 4/25/20) scheduled work activities: Excavation activities continue on the G- 1 level continued. Installation...