Construction Update - 4/16/2021

The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as we feel that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site will continue until further notice.


This past week's (4/12/21 to 4/17/21) scheduled work activities:

G2/G1

  • Drywall Framing for non-priority walls underway.

  • Installation of Elevator 3 & 4 shaft walls G-2.

  • Exterior masonry installation underway level G-2.

  • Chiller plant piping installation continues on level G-1.

  • BSL Main HVAC Duct Installation continues.

  • Lighting conduit installation continues G -1.

  • Electrical Room A build out continues level G-1.

  • In wall MEP rough in continues.

Level 1

  • Overhead HVAC ductwork installation underway.

  • Installation of glazing and frames for exterior glass underway on North Tower.

  • Installation of curtain wall frame for South Tower curtain wall underway.

  • Overhead branch HVAC duct installation underway.

  • Installation of fire suppression piping North Tower.

  • Installation of Mast climbers on exterior of building continues

Level 2

  • Sheet metal HVAC ductwork rough-in underway.

  • Installation of metal decking on center and east bridges underway.

Level 3

  • Removal of timber shoring on Level 3 pour areas 3 & 4.

  • Installation of metal decking on center and east bridges underway.

  • Frame and top out priority walls on North Tower.

  • Layout of walls and installation of top track for priority walls on South Tower.

Level 4

  • Shoring timbers in place.

Level 5

  • Shoring timbers in place.

Level 6

  • Placing and setting columns – Level 6-4.

Mechanical Penthouse

  • Forming/placing of columns for in area 6-1.

Site

  • Pouring of Concrete slabs and pads for generator yard equipment installation.

  • View of West end of building while standing in Andrews Circle.

Next week's (4/19/21 to 4/24/21) scheduled work activities:

G2 & G1

  • Overhead MEP installation continues.

  • HVAC pump skids, HEPA unit, & Heat exchangers are scheduled to be delivered.

  • Concrete equipment pads poured on G-2.

  • Non-priority wall framing continues.

  • In wall MEP rough – in continues.

  • Pneumatic tube installation begins.

Level 1

  • Overhead HVAC branch ductwork installation continues.

  • Framing & Glazing Installation North Tower.

  • Framing & Glazing Installation – South Tower.

  • Installation over overhead electrical conduit continues.

  • Installation stairs N1 & N2.

  • Installation of AWB (Air Weather Barrier coating) North Tower continues.

  • Installation of East Tower steel begins.

Level 2

  • CMU block installation – North Tower.

  • Pour concrete at Center & West bridges installation of metal decking on bridges.

Level 3

  • Frame and top out priority walls – North Tower.

  • Layout and install top track for priority walls – South Tower.

Level 4

  • Steel detailing on center bridge work continues.

Level 5

  • Shoring timbers remains in place.

Level 6

  • Installation of columns for level 6 roof/floor of mechanical penthouse.

Mechanical Penthouse

  • Concrete pours for Penthouse floor level in areas 1 & 2.

  • Rebar installation for penthouse floors level in areas 2 & 3.

  • Installation of formwork for penthouse pours in areas 3 & 4.

Site

  • Delivery and setting of APS’s to generator yard



35 views0 comments