Construction Update - 6/11/21


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. Locally, as the weekly number of new Covid cases has continued to decline, the practice of taking individuals temperatures to enter the job site has been suspended. If the total number of new cases begins to climb we will reevaluate this procedure.


This past week's (6/07/21 to 6/12/21) scheduled work activities:

G2/G1

  • Overhead MEP Installation continues. G-1 & G-2

  • Installing C channels on South end of catwalk Mezzanine over BSL3 Labs.

  • Install X braces on North & West corridor of Catwalk - G1.

  • Drywall framing installation of 7T MRI – G-1.

  • Installation of bulk sterilizers - G-1.

Level 1

  • In Wall MEP Installation continues.

  • Overhead MEP installation continues.

  • Frame soffits and hard ceilings – North Tower.

Level 2

  • Overhead MEP installation continues.

  • In wall MEP installation continues.

  • Non-priority wall framing – South Tower.

  • Installing fire suppression equipment Installation – South Tower.

  • Exterior drywall installation – South Tower.

Level 3

  • Overhead MEP Installation continues.

  • Exterior wall framing – South Tower

Level 4

  • Overhead MEP installation continues.

Level 5

  • Priority wall framing – North Tower.

Level 6

  • Overhead plumbing installation.

  • Installation of steel decking for center bridge completed ready for concrete.

Mechanical Penthouse

  • Installation/piping of Air Handling Units (AHU).

Site

  • Georgia Power made final connections of 4th transformer into HSRB – I & II main switch gears.

  • Delivery of bulk sterilizers has begun to site for installation.

Skin

  • Curtain Wall 2 glazing Installation – North Tower.

  • North facade punched openings (windows) installation.

  • North facade granite installation continues.

  • West façade CMU installation – L4 & L5.

Next week's (6/14/21 to 6/19/21) scheduled work activities:

G2 & G1

  • Granite installation will continue along Andrews Circle continues.

  • Overhead MEP installation continues G2 & G1.

  • Installation of fire suppression equipment – G-1.

  • Framing drywall in 7TMRI room – G-1.

  • Finish installation of drywall in Hot Cell room soffits G-2.

Level 1

  • Overhead MEP installation continues.

  • In wall MEP installation continues.

  • Frame soffits and hard ceilings – North Tower.

Level 2

  • Overhead MEP Installation continues.

  • In wall MEP installation continues.

  • Non-Priority wall framing South Tower.

Level 3

  • Overhead MEP work continues.

  • Installing fire suppression equipment- North Tower.

  • Exterior drywall framing – South Tower.

Level 4

  • Overhead MEP installation continues.

  • Exterior drywall framing – South Tower

Level 5

  • Priority wall framing – North Tower.

  • Exterior drywall framing – South Tower

Level 6

  • Overhead plumbing installation continues.

Mechanical Penthouse

  • Continued work on AHU’s and parapet wall

Site

  • Working continues in Micro-grid area.

Skin

  • Granite installation along Andrews Circle will continue.

  • Curtin wall 2 glazing installation continues.

  • North facade punched opening window installation continues.

  • West façade air & weather barrier (AWB) installation continues.




143 views0 comments