Construction Update - 6/5/2020


This past week's (6/1/20 to 6/6/20) scheduled work activities:

G2 Level:

  • Continuous footings & foundation walls continue

  • Pour Elevator 5 Pit

  • Install of Plumbing Underground Continues

  • Cyclotron Vault Door Frame Install

  • Service electrical duct bank to stub up at vault

G1 Level:

  • Spread footings and columns continue

  • Continuous footings & foundation walls continue

  • Waterproofing foundations continue

  • Deep underground electrical duct bank at G1 North

  • Drilled Pier Install Continues

Next week's (5/11/20 to 5/16/20) scheduled work activities:

G2 Level:

  • Continuous footings & foundation walls continue

  • Pour cyclotron walls

  • Underground Electrical and Plumbing Complete

G1 Level:

  • Spread footings and columns continue

  • Continuous footings & foundation walls continue

  • Waterproofing foundations continue

  • Deep underground electrical duct bank at G1 North



8 views0 comments