This past week's (6/1/20 to 6/6/20) scheduled work activities:
G2 Level:
Continuous footings & foundation walls continue
Pour Elevator 5 Pit
Install of Plumbing Underground Continues
Cyclotron Vault Door Frame Install
Service electrical duct bank to stub up at vault
G1 Level:
Spread footings and columns continue
Continuous footings & foundation walls continue
Waterproofing foundations continue
Deep underground electrical duct bank at G1 North
Drilled Pier Install Continues
Next week's (5/11/20 to 5/16/20) scheduled work activities:
G2 Level:
Continuous footings & foundation walls continue
Pour cyclotron walls
Underground Electrical and Plumbing Complete
G1 Level:
Spread footings and columns continue
Continuous footings & foundation walls continue
Waterproofing foundations continue
Deep underground electrical duct bank at G1 North