The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. Work will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.


This past week's (6/29/20 to 7/2/20) scheduled work activities:


G2:

  • Began bottom mat rebar installation for slab on grade pour 1

  • Preprufe waterproofing installed before slab on grade pour 1.

  • Poured Cyclotron / Hot Cell trenches

  • Continued forming of continuous foots at G-2 level near HSRB – I

G1:

  • Formed Utilidor footings

  • Last shaft drilled by loading dock

  • Preprufe the Utilidor footing

  • Continued Installation of Underground electrical conduits.

Next week's (7/6/20 to 7/11/20) scheduled work activities:


G2:

  • First slab on grade pour (A)

  • Preprufe remaining continuous footing

  • Install rebar in North West wall

G1:

  • Pour columns

  • Begin Framing and Decking G1 area A

  • Underground piping installation at North Elevator