Feb 23, 2021
Construction Update - 2/19/21
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...

emoryhsrb2
Feb 23, 2021
Construction Update - 2/12/21
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...


emoryhsrb2
Jul 31, 2020
Construction Update - 7/31/2020
The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations...


emoryhsrb2
Jun 24, 2020
Construction Update - 6/12/2020
This past week's (6/8/20 to 6/13/20) scheduled work activities: G1 Level: Spread footings & columns continue Continuous footings &...


emoryhsrb2
Jun 24, 2020
Construction Update - 6/5/2020
This past week's (6/1/20 to 6/6/20) scheduled work activities: G2 Level: Continuous footings & foundation walls continue Pour Elevator 5...


emoryhsrb2
Jun 24, 2020
Construction Update - 5/29/2020
This past week's (5/25/20 to 5/30/20) scheduled work activities: G2 Level: Spread footings and columns continue Continuous footings and...


emoryhsrb2
Jun 24, 2020
Construction Update - 5/22/2020
This past week's (5/18/20 to 5/23/20) scheduled work activities: Pour elevator 5 foundation at G-2 Level. Pour pile caps at G-2 level A...