The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. Work will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.
This past week's (7/27/20 to 8/1/20) scheduled work activities:
G2:
Pour G2 Pour B slab on grade
Form and pour remaining foundation walls
G1:
Forming of G1 Elevated Slab A continues
Footing poured at HSRB I/II interface
Continuous foundation install in G1 north continues
Columns poured in G1 south
Slab on grade preparation for G1 slab on grade pour 1
Electrical ductbank install continues
MEP underground install continues
Next week's (8/3/20 to 8/8/20) scheduled work activities:
G2:
No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.
G1:
Forming of G1 Elevated Slab A complete
Reinforcing steel install for G1 Elevated Slab A starts
Forming of G1 Elevated Slab B starts
Forming of foundation wall at HSRB I/II interface
Continuous foundation install in G1 north continues
Electrical ductbank install continues
MEP underground install continues
Pour G1 Pour 1 slab on grade