Construction Update - 6/12/2020

Writer's picture: emoryhsrb2emoryhsrb2

This past week's (6/8/20 to 6/13/20) scheduled work activities:

G1 Level:

  • Spread footings & columns continue

  • Continuous footings & foundation walls continue

  • Waterproofing foundations continue

  • Deep underground electrical duct bank at G1 North

  • Drilled pier install continues

G2 Level:

  • Continuous footings & foundation walls continue

  • Pour cyclotron walls

  • Underground electrical & plumbing resumes

Next week's (6/15/20 to 6/20/20) scheduled work activities:

G1 Level:

  • Drilled piers complete

  • Plumbing test & inspection

  • Electrical underground rough-in continues

  • Plumbing underground continues

G2 Level:

  • Pouring of columns begins

  • Continuous footings continue

  • Slab on grade preparation