This past week's (6/8/20 to 6/13/20) scheduled work activities:
G1 Level:
Spread footings & columns continue
Continuous footings & foundation walls continue
Waterproofing foundations continue
Deep underground electrical duct bank at G1 North
Drilled pier install continues
G2 Level:
Continuous footings & foundation walls continue
Pour cyclotron walls
Underground electrical & plumbing resumes
Next week's (6/15/20 to 6/20/20) scheduled work activities:
G1 Level:
Drilled piers complete
Plumbing test & inspection
Electrical underground rough-in continues
Plumbing underground continues
G2 Level:
Pouring of columns begins
Continuous footings continue
Slab on grade preparation