This past week's (5/18/20 to 5/23/20) scheduled work activities:
Pour elevator 5 foundation at G-2 Level.
Pour pile caps at G-2 level A line.
Pouring columns at G-2 Level.
Drilling and pouring caissons on G-1 level continues.
Forming and pouring G-1 level continuous & spread footings continues.
Service duct bank, deep underground electrical, and lighting protection installation is underway.
Next week's (5/11/20 to 5/16/20) scheduled work activities:
Pouring of elevator #5 pit walls.
Inspection and testing of plumbing installation at G-2 level.
Installation of Cyclotron vault door frame into wall form.
Forming and pouring continuous footings at G-2 level.
Drilling and pouring Caissons at G-1 level continues.
Spread footing waterproofing.
Installation of deep underground electrical duct bank continues.
Comments