This past week's (4/20/20 to 4/25/20) scheduled work activities:
Excavation activities continue on the G- 1 level continued.
Installation of G-1 spread footings continued.
Drilled Pier installation on G-2 level began.
Newly drilled hole
Newly drilled hole after installation of rebar cage and concrete.
G-2 elevator pit walls were poured.
G-2 underground plumbing pipe installation.
Set sleeves for electrical ductbank through G-2 foundation wall.
Waterproofing of G-2 elevator sump pits and G-1 spread footings.
Aerial photographs of the work underway this past week on site:
Next week's (4/27/20 to 5/2/20) scheduled work activities.
G2 wall pour continues.
Backfill of G1 & G2 walls begin.
G-1 spread footing pours continue.
G-1 level elevator pit walls are poured.
Pouring G-2 electrical ductbank.
Plumbing inspections and testing.
Preprufe/waterproofing installation for G-2 spread footings continues.
Comments