The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The team will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.

This past week's (9/7/20 to 9/12/20) scheduled work activities:


G2:

  • No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.

G1:

  • Concrete Slab Pour 3

  • North Concrete Wall Pour

  • Electrical and Plumbing Prep for Concrete Slab Pour 4

  • Dirt Fill for Concrete Slab Pour 2 & 4

  • Concrete Footing Pour in NW Wall

Level 1:

  • Continuing Reinforcing and Deck Forming for Elevated Concrete Deck Pour 2

  • Formwork and Inserts for Elevated Concrete Deck Pour 4

Next week's (9/14/20 to 9/19/20) scheduled work activities:


G2:

  • No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.

G1:

  • Concrete Slab Pour 2 Stone Fill

  • Concrete Slab Pour 4 Electrical Rough In

  • Concrete Slab Pour 4 Reinforcing

  • Concrete Slab Pour 4 Plumbing

  • Concrete Slab Pour 4 Waterproofing

Level 1

  • Reinforcing for Elevated Concrete Deck Pour 4