top of page
  • Writer's pictureemoryhsrb2

Construction Update - 8/7/2020


The HSRB–II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as the management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.

This past week's (8/3/20 to 8/8/20) scheduled work activities:


G2:

  • No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.

G1:

  • Reinforcing G1A elevated slab

  • Formwork for G1B elevated slab

  • G1 slab on grade pour 1

  • Forming remaining spread footings in G1

  • Forming and pouring G1 to L1 columns

  • Forming and reinforcing G1 South foundation walls

  • Forming and pouring G1 North continuous foundations

  • Continuing underground MEP install in G1

Next week's (8/10/20 to 8/15/20) scheduled work activities:


G2:

  • No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.

G1:

  • Pouring G1A elevated slab

  • Reinforcing for G1B elevated slab

  • Forming of L1 elevated slab pour 1

  • Wall pour at HSRB-I/II interface

  • MEP insert slab rough-in for G1B elevated

  • Continue forming and pouring G1 to L1 columns

  • Preprufe remaining pile caps




44 views0 comments

Recent Posts

See All
bottom of page