The HSRB–II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. The project will continue as long as the management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.
This past week's (8/3/20 to 8/8/20) scheduled work activities:
G2:
No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.
G1:
Reinforcing G1A elevated slab
Formwork for G1B elevated slab
G1 slab on grade pour 1
Forming remaining spread footings in G1
Forming and pouring G1 to L1 columns
Forming and reinforcing G1 South foundation walls
Forming and pouring G1 North continuous foundations
Continuing underground MEP install in G1
Next week's (8/10/20 to 8/15/20) scheduled work activities:
G2:
No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.
G1:
Pouring G1A elevated slab
Reinforcing for G1B elevated slab
Forming of L1 elevated slab pour 1
Wall pour at HSRB-I/II interface
MEP insert slab rough-in for G1B elevated
Continue forming and pouring G1 to L1 columns
Preprufe remaining pile caps