Construction Update - 8/28/2020

This past week's (8/24/20 to 8/29/20) scheduled work activities:


G2:

  • No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.

G1:

  • Pour G1B Elevated Slab

  • Forming G1B Elevated Slab complete

  • Reinforcing Steel install for G1B Elevated Slab complete

  • MEP insert and sleeve install for G1B Elevated Slab complete

  • G1 MEP underground rough-in continues

  • Forming and pouring of G1 continuous foundations and foundation walls continues

  • BSL3 double walled piping install

Level 1

  • Level 1 Pour 1 on Friday 8/28/20.

  • Forming Level 1 Pour 1 Elevated Slab continues

  • MEP insert and sleeve install for Level 1 Pour 1 Slab complete

  • Reinforcing steel install for Level 1 Pour 1 Elevated Slab complete

  • Forming Level 1 Pour 2 Elevated Slab complete

Next week's (8/31/20 to 9/5/20) scheduled work activities:


G2:

  • No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.

G1:

  • Pour G1B Elevated Slab

  • Subgrade preparation for G1 Slab on Grade Pour 3 continues

  • G1 MEP underground rough-in continues

  • Forming and pouring of G1 continuous foundations and foundation walls continues

Level 1

  • Rebar and Forming for Level 1 Pour 2

Sitework

  • Install sanitary sine along Haygood continues

  • HDPE stormwater piping install along Haygood continues