This past week's (8/24/20 to 8/29/20) scheduled work activities:
G2:
No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.
G1:
Pour G1B Elevated Slab
Forming G1B Elevated Slab complete
Reinforcing Steel install for G1B Elevated Slab complete
MEP insert and sleeve install for G1B Elevated Slab complete
G1 MEP underground rough-in continues
Forming and pouring of G1 continuous foundations and foundation walls continues
BSL3 double walled piping install
Level 1
Level 1 Pour 1 on Friday 8/28/20.
Forming Level 1 Pour 1 Elevated Slab continues
MEP insert and sleeve install for Level 1 Pour 1 Slab complete
Reinforcing steel install for Level 1 Pour 1 Elevated Slab complete
Forming Level 1 Pour 2 Elevated Slab complete
Next week's (8/31/20 to 9/5/20) scheduled work activities:
G2:
No major construction activities on level G-2 because this level is inaccessible due to the shoring members in place for the form work being installed for concrete pours on G-1 level above.
G1:
Pour G1B Elevated Slab
Subgrade preparation for G1 Slab on Grade Pour 3 continues
G1 MEP underground rough-in continues
Forming and pouring of G1 continuous foundations and foundation walls continues
Level 1
Rebar and Forming for Level 1 Pour 2
Sitework
Install sanitary sine along Haygood continues
HDPE stormwater piping install along Haygood continues