Construction Update - 7/30/21


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. We will continue as long as we feel that everyone on the job site can continue to do so safety. Locally, as the weekly number of new Covid cases has continued to decline, the practice of taking individuals temperatures to enter the job site has been suspended. If the total number of new cases begins to climb we will reevaluate this procedure.

This past week's (7/26/21 to 7/31/21) scheduled work activities:

G2

  • Radiopharmacy Hot Cell Installation Continues.

  • Hydraulic elevator (Elevator #3) continues.

  • Hanging of drywall continues.

G1

  • Wall framing and in wall MEP rough- in continues.

  • Overhead and in wall MEP rough in continues.

  • Pressure testing of ductwork in BSL3 lab areas is underway.

  • Wall framing on perimeter of BSL 3 lab area and in DAR vivarium

  • One sided sheet rock installation has begun in selected areas on G-1 level.

Level 1

  • In Wall MEP Installation continues, cover up inspections also underway.

  • Overhead MEP installation continues.

Level 2

  • Overhead MEP installation continues.

  • In wall MEP rough in continues.

Level 3

  • Overhead and in wall rough in of MEP Installation continues.

Level 4

  • Overhead MEP installation continues.

  • Fire suppression installation continues – North Tower.

  • Non-priority wall framing North & South towers.

  • East Pedestrian Bridge concrete pour on metal deck was completed.

Level 5

  • Overhead MEP rough in continues.

  • East pedestrian bridge detailing and decking with steel plate continues.

  • Priority wall framing completed.

Level 6

  • Overhead MEP installation continues – North & South Towers.

  • Priority wall framing continues- South Tower.

  • 6th floor East pedestrian bridge detailing and decking with metal deck continues.

Mechanical Penthouse

  • Installation of steel structures on North Tower Mechanical penthouse has begun.

Skin:

  • Glass Curtain wall #3 & #4 framing continues on West façade.

  • Glass Curtain wall #4 Framing West Façade.

  • North facade granite installation continues.

  • CMU Installation – Level 3 & 5 South Tower.

  • Installation of new High Pressure natural gas line is concluding.

Next week's (8/02/21 to 8/14/21) scheduled work activities:

G2

  • Installation of Hydraulic Elevator (Elevator #3) continues.

  • Hot Cell Installation to continue.

  • Installation of power to hot cells starts.

  • Hanging of Drywall on G-2 level continues.

G1

  • Overhead MEP Rough-in continues.

  • In wall MEP rough- in continues.

  • Catwalk and mechanical mezzanine over BSL3 & ABSL3 areas continues.

  • wall framing in BSL 3 area continues and in Vivarium (ARL) area continues.

  • Ductwork testing in BSL3 area continues.

Level 1

  • Overhead MEP installation continues.

  • In wall MEP installation continues.

  • One siding of drywall begins on this level.

Level 2

  • Overhead & In wall MEP Installation continues.

Level 3

  • Overhead & in wall rough in of MEP work continues.

Level 4

  • Overhead MEP installation continues.

  • Fire suppression equipment installation begins – North Tower.

  • Non-priority wall framing begins – South Tower.

Level 5

  • Overhead MEP installation continues.

  • East pedestrian bridge concrete pour on metal deck.

  • Fire suppression Installation continues- North Tower.

Level 6

  • Overhead MEP installation continues.

  • Priority wall framing – South Tower.

  • East pedestrian bridge detailing and metal decking.

Mechanical Penthouse

  • Continue erection of structural steel on North & South mechanical penthouses.

Skin

  • Curtin wall framing at #3 & #4 glazing – West Façade continues.

  • Granite installation – Level 1 North Façade.

  • CMU installation Level 3 South Tower.