Construction Update - 7/16/21


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. We will continue as long as we feel that everyone on the job site can continue to do so safety. Locally, as the weekly number of new Covid cases has continued to decline, the practice of taking individuals temperatures to enter the job site has been suspended. If the total number of new cases begins to climb we will reevaluate this procedure.

This past week's (7/12/21 to 7/17/21) scheduled work activities:

G2

  • Hot Cell Installation Continues.

  • Hydraulic elevator (Elevator #3) continues.

  • Hanging of drywall continues.

G1

  • Wall framing and in wall MEP rough- in continues.

  • Overhead MEP rough in continues.

  • Installation of Fire sprinkler hangers in BSL area continues.

  • Installation of mezzanine steel plates continues at ABSL3 & BSL3 area.

Level 1

  • In Wall MEP Installation continues, cover up inspections also underway.

  • Overhead MEP installation continues.

  • Installation of scaffolding in atrium to support “dance floor” at top of atrium which will allow workers in work on atrium ceiling 6 stories above continues.

  • Installation of spray on fire proofing to underside of West Pedestrian bridge.

  • Installation of in wall blocking begins.

Level 2

  • Overhead MEP installation continues.

  • In wall MEP rough in continues.

  • Frame Soffits and ceiling in South Tower.

  • Installation of metal deck and detailing Level 2 of East Pedestrian bridge.

Level 3

  • Overhead and in wall rough in of MEP Installation continues.

  • East Pedestrian Bridge slab poured on metal decking.

Level 4

  • Overhead MEP installation continues.

  • Fire suppression installation continues – North Tower.

  • Fire Suppression Installation start - South Tower.

  • East Pedestrian Bridge Detailing continues.

Level 5

  • Overhead MEP rough in continues.

  • East pedestrian bridge detailing and decking with steel plate underway.

Level 6

  • Overhead MEP installation continues – North & South Towers.

  • Priority wall framing continues- South Tower.

  • 6th floor East pedestrian bridge detailing continues.

  • Glass Curtain Wall framing on East façade continues.

Skin:

  • Glass Curtain Wall #2 glazing and trim East facade.

  • Glass Curtain wall #3 framing continues on West façade.

  • Glass Curtain wall #4 Framing West Façade.

  • North facade granite and window installationcontinues.

  • CMU Installation – Level 3 & 4 South Tower.

  • “Eyebrow” steel support installation continues on North Facade.

Next week's (7/19/21 to 7/24/21) scheduled work activities:

G2

  • Installation of Hydraulic Elevator (Elevator #3) continues.

  • Hot Cell Installation to continue.

  • Installation of power to hot cells starts.

  • Hanging of Drywall on G-2 level continues.

G1

  • Pneumatic Tube Overhead rough-in continues.

  • Overhead MEP Rough-in continues.

  • Wall Framing & in wall MEP rough- in continues.

  • Catwalk and mechanical mezzanine over BSL3 & ABSL3 areas continues.

  • Pipe installation on expansion tanks.

Level 1

  • Overhead MEP installation continues.

  • In wall MEP installation continues.

  • In wall blocking installation continues.

Level 2

  • Drywall tops out in – South Tower.

  • Overhead & In wall MEP Installation continues.

  • Install soffits and ceiling framing – South Tower.

Level 3

  • Overhead & in wall rough in of MEP work continues.

  • Installation of metal decking on East Pedestrian bridge.

Level 4

  • Overhead MEP installation continues.

  • East pedestrian bridge detailing continues.

  • East Pedestrian Bridge installation detailing continues.

Level 5

  • Overhead MEP installation continues.

  • East pedestrian bridge detailing & decking.

  • Fire suppression Installation continues- North Tower.

Level 6

  • Overhead MEP installation continues.

  • East pedestrian bridge detailing & decking.

Mechanical Penthouse

  • Installation of steel eyebrow supports continues around the perimeter.

Skin

  • Waterproofing (AWB) – South Façade.

  • Curtin wall #3 glazing – West Façade.

  • Curtin wall #4 framing – West Façade.

  • Granite installation – Level 1 North Façade.

  • CMU installation Level 4 & 5 South Tower.

  • Eyebrow support Steel installation continues on North Façade.

Site

  • Installation of New high pressure gas line continues at night down Andrews circle from 8:00 PM – 5:00 AM