top of page
Writer's pictureemoryhsrb2

Construction Update - 7/10/2020


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. Work will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site started on 4/20/20 and will continue until further notice.


This past week's (7/6/20 to 7/11/20) scheduled work activities:


G2:

  • Slab on grade Area A pour on G-2 level on Saturday 7/11/20 delayed to rain earlier in the week.

  • Complete remaining continuous footings.

  • Backfill of foundation walls continues.

G1:

  • Waterproofing installed Utilidor footings

  • G2-G1 foundation south transition continuous footings poured

  • MEP UG installation continues

Next week's (7/13/20 to 7/18/20) scheduled work activities:


G2:

  • Complete remaining foundation walls

  • Form Cyclotron lid

  • Subgrade preparation for slab on grade Area B

  • Backfill of foundation walls continues

G1:

  • Install reinforcing and pour Utilidor footings

  • G2-G1 foundation wall south transition forming and rebar install

  • MEP UG installation continues


23 views0 comments

Recent Posts

See All

Comments


bottom of page