The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. Work will continue as long as management feels that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site started on 4/20/20 and will continue until further notice.
This past week's (7/6/20 to 7/11/20) scheduled work activities:
G2:
Slab on grade Area A pour on G-2 level on Saturday 7/11/20 delayed to rain earlier in the week.
Complete remaining continuous footings.
Backfill of foundation walls continues.
G1:
Waterproofing installed Utilidor footings
G2-G1 foundation south transition continuous footings poured
MEP UG installation continues
Next week's (7/13/20 to 7/18/20) scheduled work activities:
G2:
Complete remaining foundation walls
Form Cyclotron lid
Subgrade preparation for slab on grade Area B
Backfill of foundation walls continues
G1:
Install reinforcing and pour Utilidor footings
G2-G1 foundation wall south transition forming and rebar install
MEP UG installation continues