top of page
  • Writer's pictureemoryhsrb2

Construction Update - 6/26/2020


This past week's (6/22/20 to 6/27/20) scheduled work activities:


G2:

  • Continuous footings & foundation walls continue

  • Installation of rebar and pouring of columns continue

  • Termite control, vapor barrier, rebar install, and forming of SOG

  • Continue pouring slab on grade

  • Plumbing inspections, setting drams in SOG, and Cyclotron piping

G1:

  • Continuous footings & foundation walls continue

  • Waterproofing foundations continue

  • Electrical and plumbing UG installation continues

  • South G2 to G1 Foundation Wall Transition Continues

Next week's (6/29/20 to 7/03/20) scheduled work activities:


G2:

  • Foundation wall pours continue

  • Installation of rebar and pouring of columns continue

  • Termite control, vapor barrier, rebar install, and forming of SOG

G1:

  • Spread footings continue

  • Continuous footings & foundation walls continue

  • Waterproofing foundations continue

  • Electrical install of layout boxes and inserts & slab rough-in

  • Plumbing underground piping, BSL3 piping, and setting sleeves



27 views0 comments

Recent Posts

See All
bottom of page