Construction Update - 6/25/21


The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. We will continue as long as we feel that everyone on the job site can continue to do so safety. Locally, as the weekly number of new Covid cases has continued to decline, the practice of taking individuals temperatures to enter the job site has been suspended. If the total number of new cases begins to climb we will reevaluate this procedure.

This past week's (6/21/21 to 6/26/21) scheduled work activities:

G2

  • Overhead MEP Rough in and Testing continues.

  • ADS Cabinet Steel Installed.

G1

  • Wall framing and in wall MEP rough- in continues.

  • Rough in of PLC controls begins.

  • Installation Stainless steel duct branches BSL3 area continues.

  • 1st concrete pour on section of mezzanine catwalk was completed.

  • Installation of mezzanine steel plates began.

  • Image of previously installed bulk sterilizer.

  • Work continues on elevator shafts.

Level 1

  • In Wall MEP Installation continues.

  • Overhead MEP installation continues.

  • Frame soffits and hard ceilings – South Tower, Area A.

  • Drywall installation in select areas of G-2 has begun. .

Level 2

  • Overhead MEP installation continues.

  • In wall MEP rough in underway

  • Concrete pour on level 2 East pedestrian bridge was completed.

  • Example of “Lean” building practices. Delivery & Storage no more than 4-5 day supply of materials to Job site. To keep site uncluttered.

Level 3

  • Overhead and in wall rough in of MEP Installation continues.

  • Non-Priority walls – North Tower,

  • Installation of Fire suppression equipment – North Tower, Area D.

  • Detailing of East pedestrian in prep for bridge pour.

Level 4

  • Overhead MEP installation continues.

  • Installation of Steel piping in Mechanical risers continues.

  • Exterior drywall framing continues on the North Tower

Level 5

  • Overhead MEP rough in continues.

  • Priority wall framing – South Tower.

  • Exterior drywall framing – South Tower.

  • Completed pour of center pedestrian bridge.

Level 6

  • Overhead MEP installation – North & South Towers.

  • Exterior drywall framing- South Tower.

  • Installation of the steel that supports the exterior “eyebrow” began – North Tower.

  • Completed pour of center pedestrian bridge

Mechanical Penthouse

  • Framing & Pouring of Parapet wall continues on South Penthouse level.

Skin:

  • Curtin Wall Framing & Glazing Installation on East side of –North Tower.

  • Punched Opening Fin installation – South Tower.

  • North facade granite installation continues.

  • CMU Installation – Level 2 & 6 South Façade.

Next week's (6/28/21 to 7/03/21) scheduled work activities:

G2

  • Installation of Hydraulic Elevator (Elevator #3) begins.

  • ADS Pit Lead brick installation begins.

  • Installation of lead-lined drywall in hot cell area will begin.

G1

  • Pneumatic Tube Overhead rough-in Begins.

  • Overhead MEP Rough-in continues.

  • Wall Framing & in wall MEP rough- in continues.

  • Catwalk and mechanical mezzanine over BSL3 & ABSL3 areas continues.

Level 1

  • Overhead MEP installation continues.

  • In wall MEP installation continues.

  • Frame soffits and hard ceilings – South Tower Area B.

Level 2

  • Overhead & In wall MEP Installation continues.

Level 3

  • Overhead MEP work continues.

  • Non-Priority walls- North Tower work to continue.

  • Installing fire suppression equipment- North Tower area D..

  • Installing of mechanical piping riser continues.

  • Detailing of East pedestrian bridge continues.

Level 4

  • Overhead MEP installation continues.

  • Installing of mechanical piping riser continues.

  • Exterior drywall framing continues – South Tower

  • Detailing of East pedestrian bridge continues.

Level 5

  • Overhead MEP installation continues.

  • Installation of steel piping in mechanical risers continues.

  • Priority wall framing – South Tower.

  • Exterior drywall framing – South Tower.

Level 6

  • Overhead plumbing installation continues.

  • Exterior drywall framing – South Tower.

Mechanical Penthouse

  • Continued work on AHU’s and parapet wall

Skin

  • Granite installation along Andrews Circle will continue.

  • Curtin wall installation on North Tower East elevation continues.

  • South facade CMU installation L3 & L4 West continues.

  • Punched opening fin installation continues – Northwest Façade.

  • Curtain Wall framing begins on West Façade