Construction Update - 6/18/21


The HSRB–II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. We will continue as long as we feel that everyone on the job site can continue to do so safety. Locally, as the weekly number of new COVID cases has continued to decline, the practice of taking individuals temperatures to enter the job site has been suspended. If the total number of new cases begins to climb we will reevaluate this procedure.

This past week's (6/14/21 to 6/19/21) scheduled work activities:

G2/G1

  • Overhead MEP Installation continues. G-1 & G-2

  • In wall MEP installation continues, G-1 & G-2.

  • Installation of fire suppression equipment G-1.

  • Framing Drywall in 7 T MRI room G-1.

  • Finish installation of drywall soffits in Hot Cell room. G-2.

  • Continue framing of metal Catwalk above BSL3 lab area - G1.

  • Hepa filters wrapped and waiting to be in stalled G-1.

Level 1

  • In Wall MEP Installation continues.

  • Overhead MEP installation continues.

  • Frame soffits and hard ceilings – North Tower.)

  • Installation of stainless steel HVAC riser.

Level 2

  • Overhead MEP installation continues.

  • Continue framing Non-priority walls – South Tower.

Level 3

  • Overhead MEP Installation continues.

  • Exterior wall framing – South Tower.

  • Installation of Fire suppression equipment – South Tower.

Level 4

  • Overhead MEP installation continues- North Tower.

Level 5

  • Priority wall framing – North Tower.

  • Overhead electrical rough in – North & South Towers.

  • Installation of exterior Glazing continues.

Level 6

  • Overhead MEP installation – North & South Towers.

Mechanical Penthouse

  • Framing of Parapet wall continues on South Penthouse level.

Skin:

  • Curtin Wall Framing & Glazing Installation on East side of –North Tower.

  • South facade CMU installation L-2 West.

  • North facade granite installation continues.

Next week's (6/21/21 to 6/26/21) scheduled work activities:

G2 & G1

  • Granite installation will continue along Andrews Circle continues.

  • Overhead MEP installation continues G2 & G1.

  • In wall installation of MEP continues G-2 & G-1.

  • Framing of metal catwalk continues- G1.

  • Finish installation of drywall in Hot Cell room soffits G-2.

Level 1

  • Overhead MEP installation continues.

  • In wall MEP installation continues.

  • Frame soffits and hard ceilings – North Tower.

Level 2

  • Overhead MEP Installation continues.

  • Framing of hard ceiling and soffits continues.

Level 3

  • Overhead MEP work continues.

  • Installing fire suppression equipment- North Tower.

  • Installing of mechanical piping riser continues.

Level 4

  • Overhead MEP installation continues.

  • Installing of mechanical piping riser continues.

  • Exterior drywall framing continues – South Tower

Level 5

  • Overhead MEP installation continues.

  • Priority wall framing – South Tower.

  • Installation of Stainless Steel HVAC riser continues – South Tower.

  • Exterior drywall framing – South Tower.

Level 6

  • Overhead plumbing installation continues.

Mechanical Penthouse

  • Continued work on AHU’s and parapet wall

Site

  • Working continues in Micro-grid area.

Skin

  • Granite installation along Andrews Circle will continue.

  • Curtin wall installation on North Tower East elevation continues.

  • South facade CMU installation L2-L3 West continues.