Construction Update - 5/8/2020

The HSRB – II job site is continuing to perform work on site under modified site rules that take into account the latest recommendations from the CDC. We will continue as long as we feel that everyone on the job site can continue to do so safety. The additional safety measure of taking the temperature of everyone who comes on site stated on 4/20/20 and will continue until further notice.


Last Saturday’s America Strong flyover by the Blue Angels and Thunderbirds came close enough to the project site that it was visible to JeDunn crew members working on site.





This past week's (5/4/20 to 5/9/20) scheduled work activities:


  • Mass Excavation of site continues.

  • Forming and pouring of G-1 spread and continuous footings.

  • Pouring of elevator pits on G-1 Level.

  • Installation of new waterline across Haygood began.

  • Drilling and pouring of caissons continued.

  • Installation of continuous foundation drainage.

  • Cutting and demo of overpoured footing from HSRB-I began.


Next week's (5/11/20 to 5/16/20) scheduled work activities:


  • Forming and pouring of G-1 spread and continuous footings will continue.

  • Preprufe/waterproofing membrane installation at G1 spread and continuous footings continues.

  • Backfill of foundation wall G2 continues.

  • Installation of New Waterline continues.

  • Drilling and pouring Caissons continues.

  • Forming of continuous foundation in G-2